13) No development shall take place, including any works of demolition, until a Construction Traffic Management Plan, associated with the development of the site, has been submitted and approved in writing by the Local Planning Authority which will include information on:

(A) The parking of vehicles associated with the construction within the site and where displaced staff parking will be located
(B) Loading and unloading of plant and materials used in the development
(C) Storage of plant and materials used in the development
(D) The erection and maintenance of security hoarding / scaffolding affecting the highway if required.
(E) Wheel washing facilities
(F) Measures on site to control the deposition of dirt / mud on surrounding roads during the development.
(G) Footpath/footway/cycleway or road closures needed during the development period
(H) Traffic management needed during the development period.
(I) Temporary relocation of the internal footways within the site during the construction period and/or relocation of the pedestrian access into/from the school which will be closed when the construction period is complete
(J) Deliveries outside of peak school start/finish times
The approved Construction Management Plan associated with the development of the site shall be adhered to throughout the development process.

Reason:
In the interests of safety, protecting the amenity of local land uses, neighbouring residents and highway safety.