Conditions or Reasons for Planning Application - CB/23/02647/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of drawing number; 6-9.

Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally in the interests of the visual amenities of the locality.
(Section 12, NPPF)
3) The surface water drainage shall be constructed to manage surface water runoff from the development for up to and including 1 in 100 year event (+30%CC), via discharge to an existing watercourse. The final detailed design shall be based on the agreed FRA and DS (Ref: BeforeBricks, P01, 28 November 2023), and DEFRAs Non-statutory
technical standards for sustainable drainage systems (March 2018) and shall be implemented and maintained as approved. Maintenance will ensure the system functions as designed for the lifetime of the development. Any variation to the connections and controls indicated on the approved drawing which may be necessary at the time of construction would require the resubmission of those details to the Local Planning Authority for approval.

Reason: To ensure the approved system will function to a satisfactory minimum standard of operation and maintenance and prevent the increased risk of flooding both on and off site, in accordance with CBC Local Policy CC3 to CC5 and NPPF Paras 159 to 169, inclusive of foot notes 54 to 56 and its supporting technical guidance.
4) No building shall be occupied until the developer has formally submitted in writing to the Local Planning Authority a finalised 'Maintenance and Management Plan' for the entire surface water drainage system, inclusive of any adoption arrangements and/or private ownership or responsibilities, and that the approved surface water drainage scheme has been correctly and fully installed as per the final approved details.

Reason: To ensure that the implementation and long term operation of a sustainable drainage system (SuDS) is in line with what has been approved, in accordance with Written Statement HCWS161, 18th December 2014
5) The development hereby permitted shall be undertaken in full accordance with the Councils adopted Construction Code of Practice for Developers and Contractors - November 2023 Update https://www.centralbedfordshire.gov.uk/info/44/planning/674/codes_of_practice_for_planning.

Reason: In order to minimise the impact of construction work on the amenities of nearby residential properties (Section 12, NPPF)
6) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers; 1, 2, 3, 4, 5, 6-9.

Reason: To identify the approved plan/s and to avoid doubt.