Conditions or Reasons for Planning Application - SB/00/00064
Conditions or Reasons:
1) 1. The development shall begin not later than five years from the date of this permission. REASON: To comply with Section 91 of the Town and Country Planning Act 1990. 2. Before development begins and notwithstanding the details submitted with the application, details of the materials to be used for the external walls and roofs of the building shall be submitted to and approved in writing by the District Planning Authority. REASON: To control the appearance of the building. 3. This permission relates only to the details shown on Drawing Nos. WPBC99/3/1,2 and 3 received 27/01/00 or to any subsequent appropriately endorsed revised drawings. REASON: To identify the approved drawings and to avoid doubt.


Return to Search | Close WindowTop of Page