Conditions or Reasons for Planning Application - SB/04/00171
Conditions or Reasons:
1) The development shall begin not later than five years from the date of this permission.
REASON: To comply with Section 91 of the Town and Country Planning Act 1990.
2) The external treatment of the new brickwork and the roofing materials to be used in connection with the proposed extensions shall match those of the existing building as closely as possible.
REASON: To ensure that the development is in keeping with the existing building.
(Policies 10, B.S.P.; BE8, H8, S.B.L.P.R.).
3) This permission relates only to the details shown on the Site Location Plan and Drawings Nos. 213-02-01 Rev. C, 213-02-02 Rev.C and 213-0203 received 09/02/04 or to any subsequent appropriately endorsed revised plan.
REASON: To identify the approved plan/s and to avoid doubt.


Return to Search | Close WindowTop of Page