<< Back to case
Conditions or Reasons for Planning Application - SB/04/01611
Conditions or Reasons:
1) The development shall begin not later than five years from the date of this permission.
REASON: To comply with Section 91 of the Town and Country Planning Act 1990.
2) The development shall only be carried out in complete accordance with the approved plans and specifications.
REASON: To ensure no variation from the approved plans.
(Policies 10, B.S.P & BE8 S.B.L.P.R).
3) Before the premises are occupied all on site vehicular areas shall be surfaced in a manner to the District Planning Authority¿s approval so as to ensure satisfactory parking of vehicles outside highway limits. Arrangements shall be made for surface water from the site to be intercepted and disposed of separately so that it does not discharge into the highway.
REASON: In order to minimise danger, obstruction, and inconvenience to users of the highway and of the premises.
(Policies 42 B.S.P & T1 S.B.L.P.R).
4) The development shall not be brought into use until a turning space for vehicles has been constructed within the curtilage of the site in a manner to be approved in writing by the District Planning Authority.
REASON: To enable vehicles to draw off, park and turn outside of the highway limits thereby avoiding the reversing of vehicles on to the highway.
(Policies 42 B.S.P & T1 S.B.L.P.R).
5) This permission relates only to the details shown on plan/s¿¿¿¿ received **/**/** or to any subsequent appropriately endorsed revised plan.
REASON: To identify the approved plan/s and to avoid doubt.


Return to Search | Close WindowTop of Page