| Conditions or Reasons for Planning Application - SB/05/00585/FULL |
| Conditions or Reasons: | 1)
The development shall begin not later than five years from the date of this permission. REASON: To comply with Section 91 of the Town and Country Planning Act 1990. |
2)
New external brickwork and roofing materials shall match those of the existing building as closely as possible. REASON: To ensure that the development is in keeping with the existing building. (Policies 10, B.S.P.; BE8 & H8 S.B.L.P.R). |
3)
This permission relates only to the details shown on Drawing Nos. 1,2,3,4,5,6,7,8,9,10,11,12,13,14,15 and the Site Location Plan received 06/06/05 or to any subsequent appropriately endorsed revised plan. REASON: To identify the approved plan/s and to avoid doubt. |
|
|---|