1) The development hereby approved shall be commenced within five years of the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 which is designed to ensure that a planning permission does not continue in existence indefinitely if the development to which it relates is not carried out.
2) No development shall take place until full details of both hard and soft landscape works have been submitted to and approved in writing by the Local Planning Authority and these works shall be carried out as approved. These details shall include:-

proposed finished levels or contours;
means of enclosure;
materials to be used for any hard surfacing;
proposed and existing functional services above and below ground level;
planting plans, including schedule of size, species, positions, density and times of planting;
cultivation details including operations required to establish new planting;
details of existing trees and hedgerows on the site, indicating those to be retained and the method of their protection during development works.

The landscaping works shall be undertaken in accordance with the approved plans no later than the end of the full planting season following the first occupation of the development.

Reason: In order to ensure that the landscaping is carried out within a reasonable period in the interest of the visual amenities of the area.
3) All hard and soft landscape works shall be carried out in accordance with the approved details. The works shall be carried out prior to the occupation of any part of the development or in accordance with a programme agreed in writing with the Local Planning Authority.

Reason: In order to ensure that the planting is carried out within a reasonable period in the interest of the visual amenities of the area.
4) The planting which shall have been approved consequent upon the submission of the scheme in accordance with Condition 2 above shall be carried out by a date which shall be not later than the end of the full planting season immediately following the completion of the development.

Thereafter the planting shall be adequately maintained for a period of five years from the date of planting. Any of the trees or shrubs or both which die or are removed, or which become severely damaged or seriously diseased (during the said period of five years) shall be replaced with trees or shrubs or both, as the case may be, of similar size and species to those originally required to be planted and the same shall be maintained until properly established.

Reason: In order to ensure that the planting is carried out within a reasonable period in the interest of the visual amenities of the area.
5) The plans and particulars submitted in accordance with condition 4 above shall include:-
(a) a plan showing the location of, and allocating a reference number to, each existing tree on the site which has a stem with a diameter, measured over the bark at a point 1.5 metres above ground level, exceeding 75mm, showing which trees are to be retained and the crown spread of each tree;
(b) details of the species, diameter (measured in accordance with paragraph (a) above), and the approximate height, and an assessment of the general state of health and stability, of each retained tree and of each tree which is on land adjacent to the site and to which paragraph (c) and (d) below apply:
(c) details of any proposed alterations in existing ground levels, and of the position of any proposed excavation, [within the crown spread of any retained tree or of any tree on land adjacent to the site][within a distance from any retained tree, or any tree on land adjacent to the site, equivalent to half the height of that tree];
(d) details of the specification and position of fencing [and of any other measures to be taken] for the protection of any retained tree from damage before or during the course of development.
In this condition "retained tree" means an existing tree which is to be retained in accordance with the plan referred to in paragraph (a) above.

Reason: To safeguard the existing trees on the site in the interests of visual amenity.
6) No development shall take place until details of the means of protection of the existing [tree(s)/shrubs/hedgerow(s)] on the site during building works have been submitted to and approved in writing by the Local Planning Authority, and any measures thereby approved shall be fully implemented until the development is completed.

Reason: To safeguard the long term retention of the landscaping in the interests of the visual amenities of the area.
7) No development shall take place until there has been submitted to and approved in writing by the Local Planning Authority a plan indicating the positions, design, materials and type of boundary treatment to be erected. The boundary treatment shall be completed before the building is occupied. Development shall be carried out in accordance with the approved details.

Reason: To safeguard the appearance of the completed development and the visual amenities of the locality.
8) Details of the materials to be used for the external walls and roof shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the development hereby permitted.

Reason: To protect the visual amenities of the building and of the area generally.
9) The ground floor dining room windows in the single storey element on the southern elevation of the development hereby permitted shall be fitted with obscured glass of a type to substantially restrict vision through it at all times, details of which shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. No further windows or other openings shall be formed in the elevation.

Reason: To safeguard the amenities of occupiers of adjoining properties.
10) Before the first occupation of the dwelling hereby permitted the turning space shown on plan no.1463.18/C shall be constructed in full.

Reason: To enable vehicles to draw off, park and turn outside the highway limits thereby avoiding the reversing of vehicles onto the highway.
11) Before the premises are occupied all on site vehicular areas shall be surfaced in a manner to the Local Planning Authority's approval so as to ensure satisfactory parking of vehicles outside highway limits. Arrangements shall be made for surface water from the site to be intercepted and disposed of separately so that it does not discharge into the highway.

Reason: In order to minimise danger, obstruction and inconvenience to users of the highway and of the premises.
12) Notwithstanding the provisions of the Town and Country Planning (General Permitted Development Order) 1995, (or any Order revoking or re-enacting that Order with or without modification) no works shall be commenced for the extension or material alteration of the building, or the erection of any building or structure within its curtilage, until detailed plans and elevations have been submitted to and approved in writing by the Local Planning Authority.

Reason: To protect the amenities of occupiers of neighbouring properties.
13) Before the access is first brought into use a triangular vision splay shall be provided on each side of the new access and shall measure 1.8m along the fence, wall, hedge or other means of definition of the front boundary of the site, and 1.8m measured into the site at right angles to the same line along the side of the new access drive. The vision splays so described and on land under the applicant's control shall be maintained free of any obstruction to visibility exceeding a height of 600mm above the adjoining footway level.

Reason: To provide adequate visibility between the existing highway and the proposed access, and to make the access safe and convenient for the traffic which is likely to use it.
14) Visibility splays shall be provided at the junction of the access with the public highway before the development is brought into use. The minimum dimensions to provide the required splay lines shall be 70m measured along the centre line of the proposed access from its junction with the channel of the public highway and m measured from the centre line of the proposed access along the line of the channel of the public highway. The required vision splays shall, on land in the applicant's control, be kept free of any obstruction exceeding a height of 1.05m.

Reason: To provide adequate visibility between the existing highway and the proposed access, and to make the access safe and convenient for the traffic which is likely to use it.