<< Back to case
Conditions or Reasons for Planning Application - MB/03/01017/FULL
Conditions or Reasons:
1) The development hereby approved shall be commenced within five years of the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 which is designed to ensure that a planning permission does not continue in existence indefinitely if the development to which it relates is not carried out.
2) Details of the materials to be used for the external walls and roof shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the development hereby permitted.

Reason: To protect the visual amenities of the building and of the area generally.
3) No development shall take place until full details of both hard and soft landscape works have been submitted to and approved in writing by the Local Planning Authority and these works shall be carried out as approved. These details shall include:-

proposed finished levels or contours;
means of enclosure;
materials to be used for any hard surfacing;
proposed and existing functional services above and below ground level;
planting plans, including schedule of size, species, positions, density and times of planting;
cultivation details including operations required to establish new planting;
details of existing trees and hedgerows on the site, indicating those to be retained and the method of their protection during development works.

The landscaping works shall be undertaken in accordance with the approved plans no later than the end of the full planting season following the first occupation of the development.

Reason: In order to ensure that the landscaping is carried out within a reasonable period in the interest of the visual amenities of the area.
4) The planting which shall have been approved consequent upon the submission of the scheme in accordance with Condition 3 above shall be carried out by a date which shall be not later than the end of the full planting season immediately following the first occupation of the building(s) hereby approved. Thereafter the planting shall be adequately maintained for a period of five years from the date of planting. Any of the trees or shrubs or both which die or are removed, or which become severely damaged or seriously diseased (during the said period of five years) shall be replaced with trees or shrubs or both, as the case may be, of similar size and species to those originally required to be planted and the same shall be maintained until properly established.

Reason: In order to ensure that the planting is carried out within a reasonable period in the interest of the visual amenities of the area.
5) Prior to the commencement of development, details of the design of building foundations and the layout, with positions, dimensions and levels, of service trenches, ditches, drains and other excavations on site, insofar as they may affect trees and hedgerows on or adjoining the site, shall be submitted to and approved in writing by the Local Planning Authority. Development shall be completed in accordance with the approved details.

Reason: To ensure the protection of trees and hedgerows to be retained, and in particular to avoid unnecessary damage to their root systems.
6) The proposed vehicular access shall be surfaced in tarmacadam or other similar durable material as may be approved in writing by the Local Planning Authority for a distance of 6.0m into the site, measured from the highway boundary, before the premises are occupied. Arrangements shall be made for surface water drainage from the site to be intercepted and disposed of separately so that it does not discharge into the highway.

Reason: To avoid the carriage of mud or other extraneous material or surface water from the site into the highway so as to safeguard the interest of highway safety.
7) The development shall not be brought into use until a turning space for vehicles has been constructed within the curtilage of the site in a manner to be approved in writing by the Local Planning Authority.

Reason: To enable vehicles to draw off, park and turn outside of the highway limits thereby avoiding the reversing of vehicles onto the highway.
8) No development shall commence until a wheel cleaning facility has been provided at all site exits in accordance with a scheme to be submitted to and approved in writing by the Local Planning Authority. The wheel cleaner(s) shall be removed from the site once the roadworks necessary to provide adequate access from the public highway have been completed (apart from final surfacing) to the satisfaction of the Local Planning Authority.

Reason: In the interests of the amenity and to prevent the deposit of mud or other extraneous material on the highway during the construction period.


Return to Search | Close WindowTop of Page