Conditions or Reasons for Planning Application - MB/04/01382/FULL
Conditions or Reasons:
1) The development hereby approved shall be commenced within five years of the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 which is designed to ensure that a planning permission does not continue in existence indefinitely if the development to which it relates is not carried out.
2) No development shall take place until full details of both hard and soft landscape works have been submitted to and approved in writing by the Local Planning Authority and these works shall be carried out as approved. These details shall include:-

proposed finished levels or contours;
materials to be used for any hard surfacing;
planting plans, including schedule of size, species, positions, density and times of planting;
cultivation details including operations required to establish new planting;

Reason: In order to ensure that the landscaping is carried out within a reasonable period in the interest of the visual amenities of the area.
3) All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in the first planting and seeding seasons following the occupation of the buildings or the completion of the development whichever is the sooner; and any trees or plants which within a period of 5 years of completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species unless the Local Planning Authority give written consent to any variation.

Reason: In the interests of the visual amenities of the site and the area generally.
4) No development shall take place until there has been submitted to and approved in writing by the Local Planning Authority a plan indicating the positions, design, materials and type of boundary treatment to be erected. The boundary treatment shall be completed before the building is occupied. Development shall be carried out in accordance with the approved details.

Reason: To safeguard the appearance of the completed development and the visual amenities of the locality.
5) Details of the method of disposal of foul and surface water drainage shall be submitted to and agreed in writing by the Local Planning Authority including any land drainage system, before the development is commenced. Thereafter no part of the development shall be brought into use until the approved drainage scheme has been implemented.

Reason: To ensure that adequate foul and surface water drainage is provided and that existing and future land drainage needs are protected.
6) Details of the materials to be used for the external walls and roof shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the development hereby permitted.

Reason: To protect the visual amenities of the building and of the area generally.
7) Notwithstanding the provisions of the Town and Country Planning General Permitted Development Order 1995, or any amendments thereto, the garage/carport accommodation on the site shall not be used for any purpose, other than as garage/car port accommodation, unless permission has been granted by the Local Planning Authority on an application made for that purpose.

Reason: To retain off-street parking provision and thereby minimise the potential for on-street parking which could adversely affect the convenience of road users.
8) No development shall commence until a wheel cleaning facility has been provided at all site exits in accordance with a scheme to be submitted to and approved in writing by the Local Planning Authority. The wheel cleaner(s) shall be removed from the site once the roadworks necessary to provide adequate access from the public highway have been completed (apart from final surfacing) to the satisfaction of the Local Planning Authority.

Reason: In the interests of the amenity and to prevent the deposit of mud or other extraneous material on the highway during the construction period.
9) Notwithstanding any provision of the Town and Country Planning (General Permitted Development Order) 1995 (or any Order revoking or re-enacting that Order with or without modification) no works shall be commenced for the extension of the building(s) or any material alteration of its external appearance until detailed plans and elevations have been submitted to and approved in writing by the Local Planning Authority.

Reason: To protect the amenities of occupiers of neighbouring properties.
10) Notwithstanding any provision of the Town and Country Planning (General Permitted Development) Order 1995 (or any Order revoking or re-enacting that Order with or without modification) no further window or other opening shall be formed on the east facing elevation of the building.

Reason: To protect the amenities of occupiers of neighbouring properties.