<< Back to case
Conditions or Reasons for Planning Application - SB/06/00747
Conditions or Reasons:
1) The development shall begin not later than three years from the date of this permission.
REASON: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) New external brickwork and roofing materials shall match those of the existing building as closely as possible.
REASON: To ensure that the development is in keeping with the existing building.
(Policies 10, B.S.P.; BE8 & H8 S.B.L.P.R).
3) This permission relates only to the details shown on Drawings Nos. 2137.06 and 2137.06 Rev.A received 07/07/06 and the Site Layout Plan received 12/07/06 or to any subsequent appropriately endorsed revised plan.
REASON: To identify the approved plan/s and to avoid doubt.


Return to Search | Close WindowTop of Page