Conditions or Reasons for Planning Application - SB/06/01068
Conditions or Reasons:
1) The development shall begin not later than three years from the date of this permission.
REASON: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) Before development begins, a landscaping scheme to include any hard surfaces and earth mounding shall be submitted to and approved in writing by the District Planning Authority. The approved scheme shall be implemented by the end of the full planting season immediately following the completion and/or first use of any separate part of the development (a full planting season means the period from October to March). The trees, shrubs and grass shall subsequently be maintained for a period of five years from the date of planting and any which die or are destroyed during this period shall be replaced during the next planting season and maintained until satisfactorily established.
REASON: To ensure a satisfactory standard of landscaping.
(Policies 8 & 10, B.S.P.; BE8, S.B.L.P.R).
3) The existing trees and hedgerows shall be retained and protected in a manner to be approved in writing by the District Planning Authority and shall not be destroyed, uprooted, felled, lopped or topped without the previous written consent of the District Planning Authority. Any trees or hedgerows removed without such consent or dying or being severely damaged or becoming seriously diseased shall be replaced by trees or hedgerow specimens of such size and species as may be agreed with the District Planning Authority. Such trees or hedgerow specimens shall subsequently be maintained for a period of five years from the date of planting and any which die or are destroyed during this period shall be replaced during the next planting season and maintained until satisfactorily established.
REASON: To comply with Section 197 of the Town and Country Planning Act 1990 and to safeguard existing trees on site.
(Policies 8 & 10, B.S.P.; NE4 & BE8, S.B.L.P.R).
4) Before development begins, including any ground clearance or excavation, substantial protective fencing, the details of which shall first be approved in writing by the District Planning Authority, shall be erected in the positions shown on approved Drawing No. 0612/PL-02A and the fencing shall be retained at full height and extent until the development is substantially completed. No materials shall be stored or deposited and no mixing of materials shall take place within the area so protected.
REASON: To protect the trees so enclosed in accordance with Section 8 of BS 5837 of 1991 or as may be subsequently amended.
(Policies 8 & 10, B.S.P.; NE4 & BE8, S.B.L.P.R).
5) Before the development is first occupied or brought into use, the parking scheme shown on Drawing No. 0612/PL-02A shall be completed and thereafter retained for this purpose.
REASON: To ensure provision for car parking clear of the highway.
(Policies 42, B.S.P.; T10, S.B.L.P.R).
6) Before development begins, a scheme for screen fencing and/or screen walling shall be submitted to and approved in writing by the District Planning Authority. The approved scheme shall be fully implemented before the development is first occupied or brought into use and thereafter retained.
REASON: To safeguard the amenity of the area.
(Policies 10, B.S.P.; BE8, S.B.L.P.R).
7) Before development begins and notwithstanding the details submitted with the application, details of the materials to be used for the external walls and roofs of the proposed building/s shall be submitted to and approved in writing by the District Planning Authority.
REASON: To control the appearance of the building/s.
(Policies 10, B.S.P.; BE8 & H8, S.B.L.P.R).
8) Before development begins, details of the levels of the proposed dwellings shall be submitted to and approved in writing by the District Planning Authority, and development shall thereafter be implemented accordingly.
REASON: To produce a satisfactory relationship between the various elements of the scheme and adjacent properties.
(Policy BE8, S.B.L.P.R)
9) Before development begins, the positions of the proposed dwellings shall be pegged out on site and their positions approved in writing by the District Planning Authority.
REASON: To enable consideration to be given to the precise layout of the development.
(Policies 10, B.S.P.; BE8, S.B.L.P.R).
10) Development shall not begin until details of the junction of the proposed vehicular access with the highway have been approved by the District Planning Authority and no building shall be occupied until the junction has been constructed in accordance with the approved details.
REASON: In order to minimise danger, obstruction and inconvenience to users of the highway and the premises.
(Policies 42, B.S.P.; T1, S.B.L.P.R).
11) Before the access is first brought into use a triangular vision splay shall be provided on each side of the new access and shall measure 1.8m along the fence, wall, hedge or other means of definition of the front boundary of the site, and 1.8m measured into the site at right angles to the same line along the side of the new access drive. The vision splays so described and on land under the applicant's control shall be maintained free of any obstruction to visibility exceeding a height of 600mm above the adjoining footway level.
REASON: To provide adequate visibility between the existing highway and the proposed access, and to make the access safe and convenient for the traffic which is likely to use it.
(Policies 42, B.S.P.; T1, S.B.L.P.R).
12) Visibility splays shall be provided at the junction of the access with the public highway before the development is brought into use. The minimum dimensions to provide the required splay lines shall be 2.0m measured along the centre line of the proposed access from its junction with the channel of the public highway and 90m measured from the centre line of the proposed access along the line of the channel of the public highway. The required vision splays shall, on land in the applicant's control, be kept free of any obstruction exceeding a height of 1.05m.
REASON: To provide adequate visibility between the existing highway and the proposed access(es), and to make the access(es) safe and convenient for the traffic which is likely to use it (them).
(Policies 42, B.S.P.; T1, S.B.L.P.R).
13) Before the premises are occupied all on site vehicular areas shall be surfaced in a manner to the District Planning Authority's approval so as to ensure satisfactory parking of vehicles outside highway limits. Arrangements shall be made for surface water from the site to be intercepted and disposed of separately so that it does not discharge into the highway.
REASON: In order to minimise danger, obstruction, and inconvenience to users of the highway and of the premises.
(Policies 42, B.S.P.; T1, S.B.L.P.R).
14) The turning space for vehicles illustrated on the approved Drawing No. 0612/PL-01A shall be constructed before the development is first brought into use.
REASON: To enable vehicles to draw off, park and turn outside the highway limits thereby avoiding the reversing of vehicles on to the highway.
(Policies 42, B.S.P.; T1, S.B.L.P.R).
15) Any gates provided shall open away from the highway and be set back a distance of at least 8.0m from the nearside edge of the carriageway of the adjoining highway.
REASON: To enable vehicles to draw off the highway before the gates are opened.
(Policies 42, B.S.P.; T1, S.B.L.P.R).
16) No development shall commence until wheel-cleaning facilities have been provided at all site exits in accordance with a scheme submitted to and approved in writing by the District Planning Authority. The approved facilities shall be installed and made operational before development commences and the Site Developer(s) shall ensure that all vehicles exiting the site use the approved wheel cleaning facilities. The wheel cleaning facilities shall be retained until the development has been substantially completed or until such time as the District Planning Authority is satisfied that the roadworks necessary to provide adequate and clean access to and from the public highway have been completed (apart from final surfacing).
REASON: In the interests of the amenity and to prevent the deposit of mud or other extraneous material on the highway during the construction period.
(Policies 42, B.S.P.; T1, S.B.L.P.R).
17) Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any order revoking and re-enacting that Order with or without modification), no extensions to the buildings hereby permitted shall be carried out without the grant of further specific permission from the District Planning Authority.
REASON: To control the external appearance of the buildings in the interests of the amenities of the area.
(Policies 10, B.S.P.; BE8, S.B.L.P.R).
18) Notwithstanding the provisions of Part 1 Class E of Schedule 2 to the Town and Country (General Permitted Development) Order 1995 (or any order revoking and re-enacting that Order with or without modification), no buildings or other structures shall be erected or constructed within the curtilage of the property without the grant of further specific permission from the District Planning Authority.
REASON: To control the development in the interests of the amenities of the area.
(Policies 10, B.S.P.; BE8, S.B.L.P.R).
19) Before development commences, an investigation and risk assessment of the site shall be carried out to identify possible contamination to ground, soil and sensitive receptors to determine measures necessary to remove, neutralise, and isolate such contamination. Any assessments should use the appropriate, authoritative and scientifically based guideline values. Details of such investigation, assessment and the measures proposed shall be submitted to and approved in writing by the District Planning Authority and the development shall thence proceed only in accordance with the measures as approved.
REASON: To ensure that any site contamination is dealt with safely in the interests of the health and safety of the public and users of the development hereby permitted.
(Policies BE8 & IS1, S.B.L.P.R).
20) This permission relates only to the details shown on the Site Location Plan received 27/09/06, Drawing No. 0612/PL-01B received 23/10/06, Drawings Nos. 0612/PL-03, 0612/PL-04 and 0612/PL-05 received 20/09/06 and Drawings Nos. 0612/PL-06B, 0612/PL-07B and 0612/PL-08B received 29/09/06 or to any subsequent appropriately endorsed revised plan.
REASON: To identify the approved plans and to avoid doubt.


Return to Search | Close WindowTop of Page