<< Back to case
Conditions or Reasons for Planning Application - MB/09/00293/FULL
Conditions or Reasons:
1) The development hereby approved shall be commenced within three years of the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 which is designed to ensure that a planning permission does not continue in existence indefinitely if the development to which it relates is not carried out.
2) Full details of both hard and soft landscaping shall be submitted to and approved in writing by the Local Planning Authority. These details shall include:-

materials to be used for any hard surfacing;
planting plans, including schedule of size, species, positions, density and times of planting; This shall include details of hedge planting along the frontage of the site.
cultivation details including operations required to establish new planting;
details of existing trees and hedgerows on the site, indicating those to be retained and the method of their protection during development works.

The development shall be carried out in accordance with the approved details.

Reason: In order to ensure that the landscaping is carried out within a reasonable period in the interest of the visual amenities of the area.
3) The scheme approved in Condition 2 shall be carried out by a date which shall be not later than the end of the full planting season immediately following the completion of the development.

Thereafter the planting shall be adequately maintained for a period of five years from the date of planting. Any of the trees or shrubs or both which die or are removed, or which become severely damaged or seriously diseased (during the said period of five years) shall be replaced with trees or shrubs or both, as the case may be, of similar size and species to those originally required to be planted and the same shall be maintained until properly established.

Reason: In order to ensure that the planting is carried out within a reasonable period in the interest of the visual amenities of the area.
4) A scheme shall be submitted for written approval by the Local Planning Authority indicating the positions, design, materials and type of boundary treatment to be erected. The boundary treatment shall be completed in accordance with the approved scheme before the buildings are occupied.

Reason: To safeguard the appearance of the completed development and the visual amenities of the locality.
5) All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of the existing building.

Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials to match/complement the existing building(s) and the visual amenities of the locality.
6) Notwithstanding any provision of the Town and Country Planning (General Permitted Development Order) 1995 (or any Order revoking or re-enacting that Order with or without modification)no works shall be commenced for the extension to the dwellings hereby approved until detailed plans and elevations have been submitted to and approved in writing by the Local Planning Authority.

Reason: To protect the amenities of occupiers of neighbouring properties.
7) Prior to the commencement of any phase of the development approved by this planning permission, the developer shall submit to the Planning Authority, in both paper and electronic form where possible:

a) A Phase 1 desk Study incorporating a site walkover, site history, maps and all further features of industry best practice relating to potential land contamination.

b) Where shown to be necessary by the Phase 1 desk Study, a Phase 2 Site Investigation report further documenting the ground conditions of the site with regard to potential contamination, incorporating appropriate soils, gas and groundwater sampling.

c) Where shown necessary by Phase 2 investigation, a phase 3 detailed scheme for remedial works and measures to be taken to mitigate any risks to human health, groundwater and the wider environment. Any remediation scheme shall be agreed by the local planning authority prior to the commencement of works.

d) On completion of the development, the developer shall provide written confirmation that any and all works have been completed in accordance with the agreed remediation's scheme in the form of a Phase 4 Validation Report. All variations to any remediation scheme shall be agreed in writing with the Local Planning Authority.

Reason

To protect human health and the environment.
7)
8) The proposed vehicular access shall be constructed and surfaced in accordance with details to be approved in writing by the Local Planning Authority before the premises are occupied. Arrangements shall be made for surface water drainage from the site to be intercepted and disposed of separately so that it does not discharge into the highway.

Reason: To avoid the carriage of mud or other extraneous material or surface water from the site into the highway so as to safeguard the interest of highway safety.
9) The turning space for vehicles illustrated on the approved Plan (No 1707.3) shall be constructed before the development is first brought into use.

Reason:To enable vehicles to draw off, park and turn outside of the highway limits thereby avoiding the reversing of vehicles onto the highway.
10) The permission shall extend only to the application as amended by plan dated 13/03/2009.

Reason: For the avoidance of doubt and to ensure that the development is implemented in accordance with the plans formally approved by the Local Planning Authority.


Return to Search | Close WindowTop of Page