Conditions or Reasons for Planning Application - CB/11/02801/FULL
Conditions or Reasons:
1) The development shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) Before development begins and notwithstanding the details submitted with the application, details of the materials to be used for the external walls and roofs of the proposed building/s shall be submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details.

Reason: To control the appearance of the building/s.
(Policy BE8 S.B.L.P.R).
3) Notwithstanding the provisions of the Town and Country Planning General Permitted Development Order 1995, or any amendments thereto, the garage accommodation on the site shall not be used for any purpose, other than as garage accommodation, unless permission has been granted by the Local Planning Authority on an application made for that purpose.

Reason: To retain off-street parking provision and thereby minimise the potential for on-street parking which could adversely affect the convenience of road users.
4) Before development begins, details of bin storage/collection point shall be submitted and approved in writing by the Local Planning Authority and thereafter be permanently kept available for the storage of bins.

Reason: In the interest of amenity.
5) The proposed vehicular access shall be constructed and surfaced in accordance with details to be approved in writing by the Local Planning Authority for a minimum distance of 5m into the site, measured from the highway boundary, before the premises are occupied.  Arrangement shall be made for surface water drainage from the site to be intercepted and disposed of separately so that it does not discharge into the highway.

Reason: To avoid the carriage of mud or other extraneous material or surface water from the site into the highway so as to safeguard the interest of the highway.
6) Before the access is first brought into use a triangular vision splay shall be provided on each side of the new access and shall measure 1.8m along the fence, wall, hedge or other means of definition of the front boundary of the site, and 1.8m measured into the site at right angles to the same line along the side of the new access drive. The vision splays so described and on land under the applicant's control shall be maintained free of any obstruction to visibility exceeding a height of 600mm above the adjoining footway level.

Reason: To provide adequate visibility between the existing highway and the proposed access, and to make the access safe and convenient for the traffic which is likely to use it.
7) Development shall not begin until details of the junction of the proposed vehicular access with the highway have been approved by the Local Planning Authority and no building shall be occupied until the junction has been constructed in accordance with the approved details.

Reason: In order to minimise danger, obstruction and inconvenience to users of the highway and the premises.
8) Before the access is first brought into use, a triangular vision splay shall be provided on each side of the new access drive and shall be 2.8m measured along the back edge of the highway from the centre line of the anticipated vehicle path to a point 2.0m measured from the back edge of the footway into the site along the centre line of the anticipated vehicle path. The vision splay so described and on land under the applicant's control shall be maintained free of any obstruction to visibility exceeding a height of 600mm above the adjoining footway level.

Reason: To provide adequate visibility between the existing highway and the proposed access, and to make the access safe and convenient for the traffic which is likely to use it.
9) Visibility splays shall be provided at the junction of the vehicular access with the public highway.  The splays shall extend to the limits of the site's highway frontage on each side of the access from a point on the centre line of the access measured 2.4m back from the road channel.  The vision splays so described shall be maintained free of any obstruction to visibility.

Reason: To provide adequate visibility between the existing highway and the proposed access, and to make the access safe and convenient for the traffic which is likely to use it.
10) The proposed vehicular access shall be constructed and surfaced in accordance with details to be approved in writing by the Local Planning Authority for a minimum distance of 5m into the site, measured from the highway boundary, before the premises are occupied.  Arrangement shall be made for surface water drainage from the site to be intercepted and disposed of separately so that it does not discharge into the highway.

Reason: To avoid the carriage of mud or other extraneous material or surface water from the site into the highway so as to safeguard the interest of the highway.
11) Before the new access is first brought into use, any existing access within the frontage of the land to be developed, not incorporated in the access hereby approved shall be closed in a manner to the Local Planning Authority's written approval.

Reason: In the interest of road safety and to reduce the number of points at which traffic will enter and leave the public highway.
12) The driveway length in front of the garage shall be at least 6.0m as measured from the garage doors to the highway boundary.

Reason: To ensure that parked vehicles do not adversely affect the safety and convenience of road users by overhanging the adjoining public highway.
13) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers CBC/001, 2011/0307/01, 2011/0307/02, 2011/0307/03, 2011/0307/04.

Reason: For the avoidance of doubt.