Conditions or Reasons for Planning Application - CB/11/04224/FULL
Conditions or Reasons:
1) The development shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) New external brickwork and roofing materials shall match those of the existing building as closely as possible.

Reason: To ensure that the development is in keeping with the existing building.
(Policies BE8 & H8 S.B.L.P.R).
3) Development shall not commence until a scheme detailing access provision to and from the site for construction traffic, which details shall show what arrangements will be made for restricting such vehicles to approved points of access and egress has been submitted to and approved in writing by the Local Planning Authority. The scheme shall be operated throughout the period of construction work.

Reason: To ensure the safe operation of the surrounding road network in the interests of road safety.
4) Development shall not commence until a scheme detailing provision for on-site parking for construction workers for the duration of the construction period has been submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented throughout the construction period.

Reason: To ensure adequate off street parking during construction in the interests of road safety.
5) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plan, number RM 11/129.1.

Reason: For the avoidance of doubt.


Return to Search | Close WindowTop of Page