Conditions or Reasons for Planning Application - CB/14/00654/FULL
Conditions or Reasons:
1) The development shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) The external finish of the external materials to be used for the extension shall match that of the existing building as closely as possible in type, colour and texture.

Reason: To ensure that the development is in keeping with the existing building in the interests of the visual amenities of the area.
(Policies BE8 & H8, SBLPR and Policy 43, DSCB).
3) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers 2014/0204/01, CBC/001, CBC/002.

Reason: For the avoidance of doubt.