Conditions or Reasons for Planning Application - SB/08/00312
Conditions or Reasons:
1) The works shall begin not later than three years from the date of this consent.
REASON: To comply with Section 18 of the Planning (Listed Buildings and Conservation Areas) Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) Before work begins and notwithstanding the details submitted with the application, detailed drawings of the proposed new external windows and doors showing fenestration, sections, mouldings, the relationship with the external envelope of the building, and cill/head details shall be submitted to and approved in writing by the District Planning Authority. The work shall be carried out only in accordance with the approved details.
REASON: To control the appearance of the building.
3) Before work begins and notwithstanding the details submitted with the application, details of the materials to be used for the external windows, doors, walls (including brick selection, brick bond and mortar colour, texture and pointing profile), roofs and rainwater goods of the proposed buildings shall be submitted to and approved in writing by the District Planning Authority. The work shall be carried out only in accordance with the approved details.
REASON: To control the appearance of the building.
4) This consent relates only to the details shown on Drawings Nos. 4416/SP A received 25/03/08 and 4416/P B received 15/04/08 or to any subsequent appropriately endorsed revised plan.
REASON: To identify the approved plans and to avoid doubt.