1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of the adjoining building of 34 Oldhill.

Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials to match the existing building in the interests of the visual amenities of the locality.
(Policies BE8 S.B.L.P.R and 43, D.S.C.B)
3) Before the access is first brought into use, a triangular vision splay shall be provided on each side of the new access and shall measure 1.8m along the fence, wall, hedge or other means of definition of the front boundary of the site, and 1.8m measured into the site at right angles to the same line along the side of the new access drive. The vision splays so described shall be maintained thereafter free of any obstruction to visibility exceeding a height of 600mm above the adjoining footway level.

Reason: To provide adequate visibility between the existing highway and the proposed access, and to make the access safe and convenient for the traffic which is likely to use it.
(Policies T10 S.B.L.P.R and 27 & 43, D.S.C.B)
4) Any gates provided shall open away from the highway and be set back a distance of at least 5.0m from the nearside edge of the carriageway of the adjoining highway.

Reason: To enable vehicles to draw off the highway before the gates are opened.
(Policies T10 S.B.L.P.R and 27 & 43, D.S.C.B)
5) The development shall not be occupied or brought into use until the parking scheme shown on Drawing No 2414 Rev 2 has been completed. The scheme shall thereafter be retained for this purpose.

Reason: To ensure provision for car parking clear of the highway.
(Policies T10 S.B.L.P.R and 27 & 43, D.S.C.B)
6) The premises shall not be occupied until details of the construction and surfacing of the on site vehicular access have been submitted to and approved in writing by the Local Planning Authority. These details shall include arrangements for surface water drainage from the site to soak away within the site so that it does not discharge into the highway or into the main drainage system. The access shall be constructed and surfaced in a stable and durable manner in accordance with the approved details for a distance of 5m into the site, measured from the highway boundary before the premises are first occupied.

Reason: To avoid the carriage of mud or other extraneous material or surface water from the site so as to safeguard the interest of highway safety and reduce the risk of flooding and to minimise inconvenience to users of the premises and ensure acceptable parking of vehicles outside highway limits .
(Policies T10 S.B.L.P.R and 27 & 43, D.S.C.B)
7) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers 2414 & 2414 Rev 2.

Reason: To identify the approved plans and to avoid doubt.