Conditions or Reasons for Planning Application - SB/08/00368
Conditions or Reasons:
1) The development shall begin not later than three years from the date of this permission.
REASON: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) New external brickwork and roofing materials shall match those of the existing building as closely as possible.
REASON: To ensure that the development is in keeping with the existing building.
(Policies BE8 & H8 S.B.L.P.R).
3) Before the permission hereby granted is implemented, the applicant shall enter into a Planning Agreement with the District Planning Authority pursuant to Section 106 of the Town and Country Planning Act 1990 to prevent the occupation of the permitted extension as a separate dwelling unit.
REASON: To prevent the establishment of a separate residential unit.
(Policy BE8 S.B.L.P.R).
4) This permission relates only to the details shown on Drawing No. 08:01:01 Rev A received 03/04/08 or to any subsequent appropriately endorsed revised plan.
REASON: To identify the approved drawing and to avoid doubt.