1) The development shall begin not later than three years from the date of this permission.
REASON: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) Before development begins and notwithstanding the details submitted with the application, details of the materials to be used for the external walls and roofs of the proposed building/s shall be submitted to and approved in writing by the District Planning Authority. The development shall thereafter be carried out in accordance with the approved details.
REASON: To control the appearance of the building/s.
(Policies BE8 & H8, S.B.L.P.R).
3) Before development begins, a landscaping scheme to include any hard surfaces and earth mounding shall be submitted to and approved in writing by the District Planning Authority. The approved scheme shall be implemented by the end of the full planting season immediately following the completion and/or first use of any separate part of the development (a full planting season means the period from October to March). The trees, shrubs and grass shall subsequently be maintained for a period of five years from the date of planting and any which die or are destroyed during this period shall be replaced during the next planting season and maintained until satisfactorily established.
REASON: To ensure a satisfactory standard of landscaping.
(Policy BE8, S.B.L.P.R).
4) Before development begins, details of the levels of the dwelling shall be submitted to and approved in writing by the District Planning Authority, and development shall thereafter be implemented accordingly.
REASON: To produce a satisfactory relationship between the various elements of the scheme and adjacent properties.
(Policy BE8, S.B.L.P.R).
5) Before development begins, the position of the dwelling shall be pegged out on site and its position approved in writing by the District Planning Authority.
REASON: To enable consideration to be given to the precise layout of the development.
(Policy BE8, S.B.L.P.R).
6) Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any order revoking and re-enacting that Order with or without modification), no extensions to the building/s hereby permitted shall be carried out without the grant of further specific permission from the District Planning Authority.
REASON: To control the external appearance of the building/s in the interests of the amenities of the area.
(Policy BE8, S.B.L.P.R).
7) Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any order revoking and re-enacting that Order with or without modification), no additional windows shall be inserted into either flank elevation of the proposed dwelling.
REASON: To protect the amenity of neighbouring residents.
(Policy H8, S.B.L.P.R).
8) Notwithstanding the provisions of Part 1 Class E of Schedule 2 to the Town and Country (General Permitted Development) Order 1995 (or any order revoking and re-enacting that Order with or without modification), no buildings or other structures shall be erected or constructed within the curtilage of the property without the grant of further specific permission from the District Planning Authority.
REASON: To control the development in the interests of the amenities of the area.
(Policy BE8, S.B.L.P.R).
9) Development shall not begin until details of the junction of the proposed vehicular access with the highway have been approved by the District Planning Authority and no building shall be occupied until the junction has been constructed in accordance with the approved details.
REASON: In order to minimise danger, obstruction and inconvenience to users of the highway and the premises.
10) Visibility splays shall be provided at the junction of the new access with the public highway before the development is brought into use. The minimum dimensions to provide the required splay lines shall be 2.0m measured along the centre line of the proposed access from its junction with the channel of the public highway and 43m measured from the centre line of the proposed access along the line of the channel of the public highway. The required vision splays shall, on land in the applicant's control, be kept free of any obstruction.
REASON: To provide adequate visibility between the existing highway and the proposed access and to make the access safe and convenient for the traffic which is likely to use it.
11) Before the access is first brought into use a triangular vision splay shall be provided on each side of the new access and shall measure 1.8m along the fence, wall, hedge or other means of definition of the front boundary of the site, and 1.8m measured into the site at right angles to the same line along the side of the new access drive. The vision splays so described and on land under the applicant's control shall be maintained free of any obstruction to visibility exceeding a height of 600mm above the adjoining footway level.
REASON: To provide adequate visibility between the existing highway and the proposed access(es), and to make the access(es) safe and convenient for the traffic which is likely to use it (them).
12) The proposed vehicular access shall be surfaced in bituminous or other similar durable material as may be approved in writing by the District Planning Authority for a distance of 5m into the site, measured from the highway boundary, before the premises are occupied. Arrangements shall be made for surface water drainage from the site to be intercepted and disposed of separately so that it does not discharge into the highway.
REASON: To avoid the carriage of mud or other extraneous material or surface water from the site into the highway so as to safeguard the interest of highway safety.
13) Before the premises are occupied all on site vehicular areas shall be surfaced in a manner to the District Planning Authority's approval so as to ensure satisfactory parking of vehicles outside highway limits. Arrangements shall be made for surface water from the site to be intercepted and disposed of separately so that it does not discharge into the highway.
REASON: In order to minimise danger, obstruction, and inconvenience to users of the highway and of the premises.
14) No development shall commence until wheel-cleaning facilities have been provided at all site exits in accordance with a scheme submitted to and approved in writing by the District Planning Authority. The approved facilities shall be installed and made operational before development commences and the Site Developer(s) shall ensure that all vehicles exiting the site use the approved wheel cleaning facilities. The wheel cleaning facilities shall be retained until the development has been substantially completed or until such time as the District Planning Authority is satisfied that the roadworks necessary to provide adequate and clean access to and from the public highway have been completed (apart from final surfacing).
REASON: In the interests of the amenity and to prevent the deposit of mud or other extraneous material on the highway during the construction period.
15) The development shall not begin until provision has been made to accommodate all site operatives', visitors' and construction vehicles loading, off-loading, parking and turning within the site during the construction period in accordance with details to be submitted and agreed in writing by the District Planning Authority.
REASON:To minimise danger and inconvenience to highway users.
16) Before development commences, an investigation and risk assessment of the site shall be carried out to identify possible contamination to ground, soil and sensitive receptors to determine measures necessary to remove, neutralise, and isolate such contamination. Any assessments should use the appropriate, authoritative and scientifically based guideline values. Details of such investigation, assessment and the measures proposed shall be submitted to and approved in writing by the District Planning Authority and the development shall thence proceed only in accordance with the measures as approved.
Where remediation measures are necessary a Remediation Strategy shall be provided giving full details of the remediation measures required and how they are to be undertaken. On completion of those works a verification report shall be provided confirming the remediation measures that have been undertaken in accordance with the Remediation Strategy and setting out measures for further monitoring and reporting as necessary.
If, during development, contamination not previously identified is found to be present at the site, then no further development (unless otherwise agreed in writing with the District Planning Authority) shall be carried out until the developer has submitted a Remediation Strategy or obtained written approval from the District Planning Authority for an addendum to an existing Remediation Strategy, the addendum of which must detail how this unsuspected contamination shall be dealt with and from the date of approval of the addendum(s) shall form part of the Remediation Strategy.
REASON: To ensure that any site contamination is dealt with safely in the interests of the health and safety of the public and users of the development hereby permitted.
(Policy BE8 S.B.L.P.R).
17) This permission relates only to the details shown on Drawing No. RM 07/146.2A received 15/05/08 or to any subsequent appropriately endorsed revised plan.
REASON: To identify the approved drawing and to avoid doubt.