Conditions or Reasons for Planning Application - CB/14/01976/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of the existing building.

Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials to match the existing building in the interests of the visual amenities of the locality.
(Policies BE8 and H8, SBLPR and Policy 43, DSCB)
3) The extensions, hereby approved, shall not be occupied until details of the surfacing of on site vehicular areas have been submitted to and approved in writing by the Local Planning Authority. These details shall include arrangements for surface water drainage from the site to soak away within the site so that it does not discharge into the highway.

Reason: In order to minimise danger, obstruction, inconvenience to users of the highway and the premises.
(Policies T10 and BE8, SBLPR and Policies 27 and 43, DSCB)
4) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, Job No: SC/2005396, Drawing No. 01 and 02.

Reason: To identify the approved plan/s and to avoid doubt.