Conditions or Reasons for Planning Application - SB/08/00397
Conditions or Reasons:
1) The development shall begin not later than three years from the date of this permission.
REASON: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) New external brickwork and roofing materials shall match those of the existing building as closely as possible.
REASON: To ensure that the development is in keeping with the existing building.
(Policies BE8 & H8, S.B.L.P.R.).
3) Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any order revoking and re-enacting that Order with or without modification), no windows shall be inserted into the west flank elevations of the proposed rear extension.
REASON: To protect the amenity of neighbouring residents.
(Policies BE8 & H8, S.B.L.P.R.).
4) This permission relates only to the details shown on the Site Location Plan and Drawings Nos. 276_02_01 and 276_02_02 received 9 April 2008 or to any subsequent appropriately endorsed revised plan.
REASON: To identify the approved plans and to avoid doubt.


Return to Search | Close WindowTop of Page