Conditions or Reasons for Planning Application - CB/14/03718/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) Before development/work begins and notwithstanding the details submitted with the application, details of the materials to be used for the external windows, doors, walls, roofs and rainwater goods of the proposed building/s shall be submitted to and approved in writing by the Local Planning Authority. The extensions should be finished with coping stones. The development/work shall be carried out only in accordance with the approved details.
Reason: To ensure that the development/work is in keeping with the existing building.
3) No development shall take place until drawings of all new and proposed replacement windows and doors to a scale of 1:10 or 1:20, together with a specification of the materials and finishes has been submitted to and approved in writing by the Local Planning Authority. Details provided shall clearly show a section of the glazing bars, frame mouldings, door panels, the position of the door or window frame in relation to the face of the wall, the depth of the reveal and arch and sill details. The development shall be carried out only in accordance with the approved details.
Reason: To ensure that the proposed development/work is carried out in a manner that safeguards the historic character and appearance of the area. (Policies 43 and 45, DSCB)
4) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers 02 and 03.

Reason: To identify the approved plan/s and to avoid doubt.