Conditions or Reasons for Planning Application - CB/16/01678/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of the existing building.

Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials to match the existing building in the interests of the visual amenities of the locality in accordance with policy DM3 of the Core Strategy and Development Management Policies (2009).
3) Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), no windows shall be inserted into the western flank elevation of the proposed single storey front, side and rear extension, without the grant of further specific planning permission from the Local Planning Authority.

Reason: To protect the privacy of neighbouring residents in accordance with policy DM3 of the Core Strategy and Development Management Policies (2009).
.
4) The first floor ensuite window in the side (eastern) elevation of the development hereby permitted shall be permanently fitted with obscured glass of a type to substantially restrict vision through it at all times and shall be non-opening, unless the parts of the window which can be opened are more than 1.7m above the floor of the room in which the window is installed. No further windows or other openings shall be formed in the first floor side (eastern) elevation.

Reason: To safeguard the privacy of occupiers of adjoining properties in accordance with policy DM3 of the Core Strategy and Development Management Policies (2009).
5) Before the development is brought into use, all on site vehicular areas as shown on drg no JBS/A1/07 shall be laid out and surfaced in stable and durable materials (not loose aggregate) and provision has been made for the interception and drainage of surface water from the site to soak away within the site so that it does not discharge into the highway or into the main drainage system.

Reason: To avoid the carriage of mud or other extraneous material or surface water from the site so as to safeguard the interest of highway safety and reduce the risk of flooding and to minimise inconvenience to users of the premises and ensure satisfactory parking of vehicles outside highway limits in accordance with Policy DM3 of the Core Strategy and Development Management Policies (2009).
6) Notwithstanding the provisions of the Town and Country Planning General Permitted Development Order 2015, or any amendments thereto, the garage accommodation on the site shall not be used for any purpose, other than as garage accommodation, unless permission has been granted by the Local Planning Authority on an application made for that purpose.

Reason: To retain off-street parking provision and thereby minimise the potential for on-street parking which could adversely affect the convenience of road users.
7) The proposed development shall be carried out and completed in all respects in accordance with the access widening, siting and layout and parking provision layout illustrated on the approved drawing no. JBS/A1/07, before the development is brought into use, and defined by this permission and, notwithstanding the provision of the Town and Country Planning General Permitted Development Order 2015, (or any Order revoking or re-enacting that Order) there shall be no variation without the prior approval in writing of the Local Planning Authority.

Reason: To ensure that the development of the site is completed insofar as its various parts are interrelated and dependent one upon another and to provide adequate and appropriate access arrangements at all times.
8) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers JBS/A1/01, JBS/A1/06, JBS/A1/07.

Reason: To identify the approved plan/s and to avoid doubt.