| Conditions or Reasons: | 1)
The development hereby permitted shall begin not later than three years from the date of this permission.
Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
2)
All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of the existing building.
Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials to match the existing building in the interests of the visual amenities of the locality. (Policy BE8, SBLPR and Section 7, NPPF) |
3)
The extensions hereby approved shall not be first occupied or brought into use until a scheme for the parking of vehicles on the site has been submitted to and approved in writing by the Local Planning Authority. The scheme shall comply with the standards of the Local Planning Authority and shall be fully implemented before either of the extensions hereby approved is first occupied or brought into use and thereafter retained for this purpose.
Reason: To ensure provision for car parking clear of the public highway in the interests of road safety. (Policies BE8 & T10, SBLPR and Section 4, NPPF) |
4)
The extensions hereby permitted shall not be first occupied or brought into use until a scheme for the parking of cycles on the site has been submitted to and approved in writing by the Local Planning Authority. The scheme shall be fully implemented before the development is first occupied or brought into use and thereafter retained for this purpose.
Reason: To ensure the provision of cycle parking to meet the needs of occupiers of the proposed development in the interests of encouraging the use of sustainable modes of transport. (Policy BE8, SBLPR and Section 4, NPPF) |
5)
No development shall take place until a scheme detailing provision for on site parking for construction workers and deliveries for the duration of the construction period has been submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented throughout the construction period.
Reason: The condition must be discharged prior to commencement to ensure adequate off street parking during the construction period in the interests of road safety. (Policy BE8, SBLPR and Section 4, NPPF) |
6)
Before the building is first brought into use, an updated Travel Plan shall be prepared and submitted to and approved by the Local Planning Authority. The plan shall contain details of:
plans for the establishment of a working group involving the School, parents and representatives of the local community pupil travel patterns and barriers to sustainable travel measures to encourage and promote sustainable travel and transport for journeys to and from school an action plan detailing targets and a timetable for implementing appropriate measures and plans for annual monitoring and review measures to manage the car parking on site
All measures agreed therein shall be undertaken in accordance with the approved plan. There shall be an annual review of the Travel Plan to monitor progress in meeting the targets for reducing car journeys generated by the proposal and this shall be submitted to and approved by the Local Planning Authority.
Reason: In the interests of highway safety, to reduce congestion and to promote the use of sustainable modes of transport (Policies BE8 & T10, SBLPR and Section 4, NPPF) |
7)
The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers 1001, 1002, 2000, 2001, 2002, 2003, 2004, 3001, 3002, 3003, 3004, 3005 and 3006.
Reason: To identify the approved plans and to avoid doubt. |
|
|---|