Conditions or Reasons for Planning Application - CB/16/02094/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) No development shall take place, notwithstanding the details submitted with the application, until details of the materials to be used for the external walls and roofs of the development hereby approved have been submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details.

Reason: Building materials are required in advance of the construction phase to ensure that the materials proposed would reflect the envisaged appearance of the development in the interest of visual amenity.
(Section 12, NPPF)
3) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers P-P101, PP-P002, P-E201, P-E202, P-S001, P-S003, P-R301

Reason: To identify the approved plan/s and to avoid doubt.