<< Back to case
Conditions or Reasons for Planning Application - CB/16/03935/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) No development shall take place until a written scheme of archaeological investigation; that includes provision for post excavation analysis and publication, has been submitted to and approved in writing by the Local Planning Authority. The development hereby approved shall only be implemented in full accordance with the approved archaeological scheme.'

Reason: This condition is pre-commencement as a failure to secure appropriate archaeological investigation in advance of development would be contrary to paragraph 141 of the NPPF which requires developers to record and advance understanding of the significance of any heritage assets with archaeological interest which will be unavoidably affected as a consequence of the development, and to make the record of this work publicly available.

This pre-commencement condition is necessary in order to ensure that no unnecessary harm is caused by the commencement of development works.
2) No development shall take place until a written scheme of archaeological investigation; that includes provision for post excavation analysis and publication, has been submitted to and approved in writing by the Local Planning Authority. The development hereby approved shall only be implemented in full accordance with the approved archaeological scheme.'

Reason: This condition is pre-commencement as a failure to secure appropriate archaeological investigation in advance of development would be contrary to paragraph 141 of the NPPF which requires developers to record and advance understanding of the significance of any heritage assets with archaeological interest which will be unavoidably affected as a consequence of the development, and to make the record of this work publicly available.

This pre-commencement condition is necessary in order to ensure that no unnecessary harm is caused by the commencement of development works.
3) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers Figure 1 (location plan); Figure 2 (block plan); Figure 3 (fence elevations).

Reason: To identify the approved plan/s and to avoid doubt.


Return to Search | Close WindowTop of Page