<< Back to case
Conditions or Reasons for Planning Application - CB/16/04867/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) Before development/work begins and notwithstanding the details submitted with the application, details of the materials to be used for the external windows, walls, roofs, rooflights and rainwater goods of the proposed building/s shall be submitted to and approved in writing by the Local Planning Authority. The development/work shall be carried out only in accordance with the approved details.

Reason: To ensure that the development/work is in keeping with the character of the Woburn Conservation Area.
(Section 12, NPPF)

A pre-commencement condition is required to safeguard the development as it is within the Woburn Conservation Area, the materials to be used are of crucial importance to the acceptability of the scheme.
3) The first floor window in the south east (side) facing elevation of the development hereby permitted shall be permanently fitted with obscured glass of a type to substantially restrict vision through it at all times and shall be non-opening, unless the parts of the window(s) which can be opened are more than 1.7m above the floor of the room(s) in which the window(s) is installed.

Reason: To safeguard the privacy of occupiers of adjoining properties
(Section 7, NPPF)
4) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers site plan, STAN/10P/Sk(A)16A, STAN/20P/Sk(A)16A.

Reason: To identify the approved plans and to avoid doubt.


Return to Search | Close WindowTop of Page