Conditions or Reasons for Planning Application - CB/17/01884/LB
Conditions or Reasons:
1) The works shall begin not later than three years from the date of this consent.

Reason: To comply with Section 18 of the Planning (Listed Buildings and Conservation Areas) Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) Following the carrying out or completion of the building operations or alterations for which consent is hereby granted, all making good of the existing building shall be carried out in materials & finishes which closely match, like-for-like, those historic materials & finishing details used in the existing building or structure- to accord with usual conservation good practice & to the satisfaction of the Local Planning Authority. If there is any doubt regarding the approach to any proposed making good, or any alternative materials are proposed, a precise specification of the materials & finishes should be submitted to & agreed in writing by the Local Planning Authority.

Reason: To ensure that the special architectural & historic interest, character & appearance of the building is properly maintained, in accordance with standard conservation good practice. Core Strategy Policy CS15.
3) Before development/work begins and notwithstanding the details submitted with the application, details of the materials to be used for the external windows, doors, walls, roofs and rainwater goods of the proposed building/s and a clear schedule of all external material finishes shall be submitted to and approved in writing by the Local Planning Authority. The development/work shall be carried out only in accordance with the approved details.
Reason: To ensure that the development/work is in keeping with the existing building. (Section 12, NPPF)
4) No development shall take place until drawings of all new and proposed replacement windows and doors to a scale of 1:10 or 1:20, together with a specification of the materials and finishes has been submitted to and approved in writing by the Local Planning Authority. Details provided shall clearly show a section of the glazing bars, frame mouldings, door panels, the position of the door or window frame in relation to the face of the wall, the depth of the reveal and arch and sill details. The development shall be carried out only in accordance with the approved details.
Reason: To ensure that the proposed development/work is carried out in a manner that safeguards the historic character and appearance of the area.
(Section 12, NPPF)
5) No development shall take place until detailed drawings of the construction of the roof dormer and timber porch hereby approved to a scale of 1:10 or 1:20, together with a specification of the materials and finishes has been submitted to and approved in writing by the Local Planning Authority. Details provided shall clearly show clear sections and elevations of the construction of the rear dormer window and timber porch in relation to the existing fabric of the building, including glazing bars, frame mouldings, door panels, the position of the door or window frame in relation to the face of the wall, the depth of the reveal and arch and sill details. The development shall be carried out only in accordance with the approved details.
Reason: To ensure that the proposed development/work is carried out in a manner that safeguards the historic character and appearance of the area.
(Section 12, NPPF)
6) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers CBC/01; 27616/01; 27616/02; 27616/03A; 27616/04E; 27616/05D; 27616/06G; 27616/07E; 27616/08; 27616/09A; 27616/10D; Design, Access and Heritage Statement


Reason: To identify the approved plan/s and to avoid doubt.


Return to Search | Close WindowTop of Page