Conditions or Reasons for Planning Application - CB/17/01934/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) A vehicular cross-over and two nos. parking spaces for two nos. vehicles on the site, clear of the highway, as shown on the submitted plan with the drawing number F01/ Rev. B, shall be provided. This parking area shall be surfaced in a stable and durable material and arrangements shall be made for surface water drainage from the site to soak away within the site so that it does not discharge into the highway or into the main drainage system. The above cross-over and parking spaces shall be fully implemented before the development hereby approved is first occupied or brought into use, and thereafter retained for this purpose.

Reason: To minimise the potential for on-street parking, ensure satisfactory parking of vehicles outside highway limits, and to avoid the carriage of mud or other extraneous material or surface water from the site so as to safeguard the interest of highway safety, reduce the risk of flooding and to minimise inconvenience to users of the premises and road users.
(Policy T10, SBLPR and Section 4, NPPF)
3) All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of the existing building.

Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials to match the existing building in the interests of the visual amenities of the locality.
(Policies BE8 and H8, SBLPR and Section 7, NPPF)
4) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers F97, F98/ Rev. A , F99, F001, F002, F01/ Rev. B and F02/ Rev. B.

Reason: To identify the approved plans and to avoid doubt.


Return to Search | Close WindowTop of Page