Conditions or Reasons for Planning Application - CB/17/03630/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) Before development/work begins and notwithstanding the details submitted with the application, details of the materials to be used for the advertisement lettering (both to the front of the building and the gable end) shall be submitted to and approved in writing by the Local Planning Authority. The development/work shall be carried out only in accordance with the approved details.
Reason: To ensure that the development/work is in keeping with the existing building and wider Conservation Area.
(Policy BE8, SBLPR & Sections 7 & 12, NPPF)
3) The internalisation of the shutters shown on drawing no. LB5-PL-P-010 Rev 02 shall be completed in accordance with the approved details prior to the completion of the remainder of works hereby approved.

Reason: To ensure that the development/work is in keeping with the existing building and wider Conservation Area.
(Policy BE8, SBLPR & Section7 & 12, NPPF)
4) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers LB5-PL-E-001 Rev 01, LB5-PL-D-010 Rev 02, LB5-PL-D-011 Rev 02, LB5-PL-E-011 Rev 02, LB5-PL-P-010 Rev 02, LB5-PL-P-011 Rev 02 & LB5-PL-E-010 Rev 02.

Reason: To identify the approved plans and to avoid doubt.