1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of the existing building.

Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials to match the existing building in the interests of the visual amenities of the locality.
(Section 7, NPPF)
3) No drainage works shall commence until a surface water management strategy has been submitted to and approved in writing by the Local Planning Authority. No hard-standing areas to be constructed until the works have been carried out in accordance with the surface water strategy so approved unless otherwise agree in writing by the Local Planning Authority.

Reason: To prevent environmental and amenity problems arising from flooding.
4) Prior to the development being brought into use a revised travel plan shall be submitted to and approved in writing by the local planning authority and any improvements and/or requirements established in the approved details shall be implemented within an agreed time scale between the school and the local planning authority

Reason: To promote sustainable modes of travel and to reduce the potential traffic impact of the development on the local highway network
5) Before the development is brought into use, all on site vehicular areas shall be surfaced in stable and durable materials in accordance with details to be approved in writing by the Local Planning Authority. Arrangements shall be made for surface water drainage from the site to soak away within the site so that it does not discharge into the highway or into the main drainage system.

Reason: To avoid the carriage of mud or other extraneous material or surface water from the site so as to safeguard the interest of highway safety and reduce the risk of flooding and to minimise inconvenience to users of the premises and ensure satisfactory parking of vehicles outside highway limits
6) Prior to occupation details of measures to improve school safety such as school keep clear markings, 20mph speed reduction and parking restrictions shall be submitted to and approved in writing by the local planning authority, such measures to be implemented within 6 months of the local roads being adopted as publicly maintained highway.

Reason: As measures to improve safety in the vicinity of the school, for users of the property and the highway.
7) The construction of this development shall be carried out in accordance with the details set out within the Environmental Plan Modplan Document 2017 and the Site Waste Management Plan Version 1 dated October 2017, unless otherwise agreed in writing by the Local Planning Authority.

Reason: To ensure safe construction practice during the development of the site.
8) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers 01, PL01, PL02A, PL03, PL04, Environmental Plan - Modplan October 2017, Site Waste Management Plan Version 1 October 2017, Supporting Statement.

Reason: To identify the approved plan/s and to avoid doubt.