Conditions or Reasons for Planning Application - CB/17/04187/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of the existing building.

Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials to match the existing building in the interests of the visual amenities of the locality.
(Policies BE8 & H8, SBLPR and Section 7, NPPF)
3) Prior to development, all protective measures are to be installed in strict accordance with the plan drawing "Tree Protection Plan" (Drawing No. Arbtech TPP 01) and the section "Protective Measures" of the "Arboricultural Method Statement" (Document Ref. AMS 01 - Issue 2). The protective measures shall then remain firmly in place until completion of Stage 8 of the "Sequencing of Works" as outlined in the "Arboricultural Method Statement".

Reason: To ensure that a satisfactory standard of physical tree protection is set up and maintained throughout the course of development, including demolition.
(Policy BE8, SBLPR and Sections 7 & 11, NPPF)
4) Both prior to and during development. all recommended working procedures and operations shall be fully implemented in strict accordance with the "Arboricultural Method Statement" Ref. AMS 01 (Issue No 2), as set out under the specified "Sequence of Works" and under the appropriate arboricultural supervision where stipulated.

Reason: To ensure that appropriate working practices are undertaken in accordance with good arboricultural practice, as set out in the "Arboricultural Method Statement", to ensure the continued protection of retained trees throughout the course of development activity, including demolition.
(Policiy BE8, SBLPR and Sections 7 & 11, NPPF)
5) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers 2962-01c and Location Plan.

Reason: To identify the approved plans and to avoid doubt.