| Conditions or Reasons for Planning Application - CB/18/00194/FULL |
| Conditions or Reasons: | 1)
The development hereby permitted shall begin not later than three years from the date of this permission.
Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
2)
All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of the existing building.
Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials to match the existing building in the interests of the visual amenities of the locality. (Policies BE8 & H8, SBLPR, Policy HQ1, submission of the Local Plan 2015-2035 and Section 7, NPPF) |
3)
Notwithstanding the provisions of Part 1, Class A, Class B & Class C of Schedule 2 to the Town and Country Planning (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), no extensions or alteration to the building hereby permitted shall be carried out without the grant of further specific planning permission from the Local Planning Authority.
Reason: To control the external appearance of the building/s in the interests of the amenities of the area.
(Policies BE8 & H8, SBLPR, Policy HQ1, submission of the Local Plan 2015-2035 and Section 7, NPPF) |
4)
The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers ATK/17/2DR/TP1, ATK/17/2DR/TP2, ATK/17/2DR/TP3, ATK/17/2DR/TP4 and ATK/17/2DR/TP5.
Reason: To identify the approved plans and to avoid doubt. |
|
|---|