Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) Development shall not take place above base course level until details of the materials to be used for the external parts of the buildings hereby approved have been submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details.

Reason: To control the appearance of the building in the interests of the visual amenities of the locality.
(Section 7, NPPF).
3) No development shall take place until details of the existing and final ground and slab levels of the buildings hereby approved have been submitted to and approved in writing by the Local Planning Authority. Such details shall include sections through both the site and the adjoining properties, the location of which shall first be agreed in writing with the Local Planning Authority. Thereafter the site shall be developed in full accordance with the approved details.

Reason: A pre commencement condition is required to ensure that an acceptable relationship results between the new development and adjacent buildings and public areas. (Section 7, NPPF)
4) The first floor window in the front elevation of the development hereby permitted shall be permanently fitted with obscured glass of a type to substantially restrict vision through it at all times and shall be non-opening. The rooflights in the front elevation shall also be obscured glass of a type to substantially restrict vision through them at all times and shall be non-opening, unless the parts of the window(s) which can be opened are more than 1.7m above the floor of the room(s) in which the window(s) is installed.

Reason: To safeguard the privacy of occupiers of the adjoining property (No.139 Grange Road).
(Section 7, NPPF)
5) No development shall take place until a landscaping scheme to include all hard and soft landscaping and a scheme for landscape maintenance for a period of five years following the implementation of the landscaping scheme have been submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented by the end of the full planting season immediately following the completion and/or first use of any separate part of the development (a full planting season means the period from October to March). The trees, shrubs and grass shall subsequently be maintained in accordance with the approved landscape maintenance scheme and any which die or are destroyed during this period shall be replaced during the next planting season.

Reason: To ensure an acceptable standard of landscaping.
(Sections 7 & 11, NPPF)
6) No equipment, machinery or materials shall be brought on to the site for the purposes of development until details of substantial protective fencing for the protection of any retained tree(s), has been submitted to and approved in writing by the Local Planning Authority and the fencing has been erected in the positions shown. The approved fencing shall be maintained until all equipment, machinery and surplus materials have been removed from the site. Nothing shall be stored or placed in any area fenced in accordance with this condition and the ground levels within those areas shall not be altered, nor shall any excavation be made.

Reason: A pre commencement condition is required to protect the trees so enclosed in accordance with Section 8 of BS 5837 of 2012 or as may be subsequently amended. (Sections 7 & 11, NPPF)
7) Planning permission is being granted in recognition that no underground services are scheduled to be routed through the Root Protection Areas of the retained trees and/or hedgerows (as identified by the Tree Survey Plan). If any services are subsequently required to be routed through the designated area protected under the Tree Protection Plan, then this work shall be carried out in full accordance with the National Joint Utilities Group (NJUG) Volume 4 Guidelines for the Planning, Installation and Maintenance of Utility Apparatus in Proximity to Trees.

Reason: To safeguard existing trees and hedgerows.
(Sections 7 & 11, NPPF)
8) A scheme shall be submitted for approval in writing by the Local Planning Authority indicating the positions, design, materials and type of boundary treatment to be erected. The boundary treatment shall be completed in accordance with the approved scheme [before the use hereby permitted is commenced / before the building(s) is/are occupied] and be thereafter retained.

Reason: To safeguard the appearance of the completed development and the visual amenities of the locality.
(Section 7, NPPF)
9) The proposed dwelling shall not be occupied until the means of access and parking areas have been laid out, drained and surfaced in accordance with details to be submitted to and approved in writing by the Local Planning Authority and those areas shall not thereafter be used for any other purpose.

Reason: To provide a satisfactory means of access and to enable vehicles to draw off and park clear of the access road to minimise conditions of danger, obstruction and inconvenience to users of the adjoining access road. (Section 7, NPPF)
10) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers GT01, GT02, GT03,GT04.

Reason: To identify the approved plan/s and to avoid doubt.