| Conditions or Reasons for Planning Application - CB/18/03461/FULL |
| Conditions or Reasons: | 1)
The development hereby permitted shall begin not later than three years from the date of this permission.
Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
2)
No development shall take place until a Construction Traffic Management Plan (CTMP) has been submitted to and approved in writing by the Local Planning Authority. The CTMP shall include proposals for construction traffic routes, the scheduling and timing of movements, any traffic control, signage within the highway inclusive of temporary warning signs, the management of junctions to, and crossing of, the public highway and other public rights of way, details of escorts for abnormal loads, temporary removal and replacement of highway infrastructure and street furniture, the reinstatement of any signs, verges or other items displaced by construction traffic, banksman and escort details, including tracking diagrams at junctions. Details shall be submitted indicating the off-street parking areas for site operatives and visitors and areas for the loading and unloading of plant and materials. The CTMP shall be implemented in accordance with the approved details for the duration of the construction period.
Reason: In order to minimise danger, obstruction and inconvenience to users of the highway and the site.
This pre-commencement condition has been agreed with the applicant as it is necessary in order to ensure that no unnecessary harm is caused by the commencement of development works. |
3)
All works shall be carried out in accordance with the details contained in the July 2018 Biodiversity Checklist as already submitted with the planning application and agreed in principle with the local planning authority prior to determination.
Reason: To identify the document and to avoid doubt. |
4)
All plant, machinery and equipment installed or operated in connection with this permission shall be so enclosed, operated and/or attenuated that noise arising from such shall not exceed a level of 65dBA LAeq at a distance of 10 metres in any direction and under all modes of operation.
Reason: To protect the amenity of residential units in the vicinity |
5)
The hours of use shall be be restricted to 2000 hours per annum as stated in the Planning Design & Access Statement (September 2018). Reason: To safeguard the residential amenity of neighbouring properties. (Section 12, NPPF) |
6)
The development hereby permitted shall be removed and recycled and the site restored at the end of its operational life of 25 years.
Reason: For the avoidance of doubt and to protect the openness of the Green Belt (Section 13, NPPF) |
7)
The planting and landscaping scheme shown on approved Drawing No. 799-CSU02 Rev F shall be implemented by the end of the full planting season immediately following the completion and/or first use of any separate part of the development (a full planting season shall mean the period from October to March).
Following the completion of the Planting and Landscaping scheme details including photos etc shall be submitted to and approved in writing by the Local Planning Authority. The trees, shrubs and grass shall subsequently be maintained for a period of five years from the date of planting and any which die or are destroyed during this period shall be replaced during the next planting season with others of a similar size and species.
Reason: To ensure an acceptable standard of landscaping. (Sections 12 & 15, NPPF) |
8)
The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers Sundon GA-002-TB (elevations); CSU11 Site block plan; CSU 03-10 Principle Viewpoints; CSU 02B Landscape Masterplan; BE5320-D04 location plan.
Reason: To identify the approved plan/s and to avoid doubt. |
|
|---|