Conditions or Reasons for Planning Application - CB/18/03757/LB
Conditions or Reasons:
1) The works shall begin not later than three years from the date of this consent.

Reason: To comply with Section 18 of the Planning (Listed Buildings and Conservation Areas) Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) Before development/work begins and notwithstanding the details submitted with the application, details of the materials to be used for the external windows, doors, walls, roofs and rainwater goods of the proposed building/s shall be submitted to and approved in writing by the Local Planning Authority. The development/work shall be carried out only in accordance with the approved details.
Reason: To ensure that the development/work is in keeping with the existing building. (Section 16, NPPF)