<< Back to case
Conditions or Reasons for Planning Application - CB/19/00133/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of the existing building.

Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials to match the existing building in the interests of the visual amenities of the locality.
(Section 12, NPPF)
3) The development shall not be occupied until details of the alterations of the vehicular access onto Queens Street have been approved by the Local Planning Authority and no building shall be occupied until the access has been constructed in accordance with the approved details. This vision splay shall be provided on each side of the access drive and shall be 2.8m measured along the back edge of the new highway from the centre line of the anticipated vehicle path to a point 2.0m measured from the back edge of the footway into the site along the centre line of the anticipated vehicle path. The vision splay so described and on land under the dwelling occupier's control shall be maintained free of any obstruction to visibility exceeding a height of 600mm above the adjoining footway level.

Reason: To provide adequate visibility between the new estate road and the new individual accesses, and to make the accesses safe and convenient for the traffic which is likely to use them.
(Section 9, NPPF)
4) Any gates provided shall open away from the highway and be set back a distance of at least 5.0m (domestic)/8.0 metres (agricultural) from the nearside edge of the carriageway of the adjoining highway.

Reason: To enable vehicles to draw off the highway before the gates are opened.
(Section 9, NPPF)
5) The development shall not be occupied until details of refuse storage area and collection point have been approved by the Local Planning Authority and no building shall be occupied until the said storage and collection points have been constructed in accordance with the approved details.

Reason: To ensure the refuse collection bins do not cause a hazard or obstruction to the highway or parking area.
(Section 9, NPPF)
6) The development shall not be occupied until details of secure cycle storage for residents and cycle parking for visitors have been approved by the Local Planning Authority and no building shall be occupied until the said storage and parking have been constructed in accordance with the approved details.

Reason: In order to promote sustainable modes of transport
(Section 9, NPPF)
7) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers TLD 001, TLD 002, TLD 011, TLD 012, TLD 013, TLD 014, TLD 015, TLD 016, TLD 121, TLD 022, TLD 023, TLD 024, TLD 025 and TLD 026.

Reason: To identify the approved plan/s and to avoid doubt.
8) Notwithstanding the submitted details, the number of residents (not including staff) present at any one time shall not exceed more than 12.

Reason: In the interest of safeguarding the amenity of neighbouring residents.
(Section 12, NPPF)


Return to Search | Close WindowTop of Page