Conditions or Reasons for Planning Application - CB/19/00739/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) No development above ground shall take place until details of the junctions of the proposed vehicular accesses with the highway have been approved by the Local Planning Authority and no building shall be occupied until the junctions have been constructed in accordance with the approved details.

Reason: In order to minimise danger, obstruction and inconvenience to users of the highway and the premises.
3) Before the access is brought into use an area of land across the whole of the site frontage measuring at least 2.4m from and parallel to the nearside edge of the adjacent carriageway shall be provided and thereafter be kept free of all obstruction to visibility.

Reason: To provide adequate visibility between the existing highway and the proposed accesses and to make the accesses safe and convenient for the traffic which is likely to use them.
4) The proposed driveway shall be constructed and surfaced in a stable and durable material for a minimum distance of 5m into the site, measured from the highway boundary, before the premises are occupied.  Arrangement shall be made for surface water drainage from the site to be intercepted and disposed of separately so that it does not discharge into the highway.

Reason: To avoid the carriage of mud or other extraneous material or surface water from the site into the highway so as to safeguard the interest of the highway.
5) Any gates provided shall open away from the highway and be set back a distance of at least 5.0m from the nearside edge of the carriageway of the adjoining highway.

Reason: To enable vehicles to draw off the highway before the gates are opened.
6) Notwithstanding the provisions of Part 1, Class A of Schedule 2 to the Town and Country Planning (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), no extensions to the building(s) hereby permitted shall be carried out without the grant of further specific planning permission from the Local Planning Authority.

Reason: To control the external appearance of the building in the interests of the openness of the Green Belt.
(Section 13, NPPF)
7) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers P1; P2; P3;P4; P5; P6.

Reason: To identify the approved plan/s and to avoid doubt.