<< Back to case
Conditions or Reasons for Planning Application - CB/19/01655/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) No development shall take place until samples of the materials to be used in the construction of the external surfaces of the development hereby permitted have been submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details.

Reason: To control the appearance of the building in the interests of the visual amenities of the locality. This condition requires discharging pre-commencement due to the importance of agreeing the appearance of the building prior to any form of development, minimising any harmful visual impact.
(Section 12, NPPF)
3) The development shall not be brought into use until a landscaping scheme to include all hard and soft landscaping and a scheme for landscape maintenance for a period of five years following the implementation of the landscaping scheme have been submitted to and approved in writing by the Local Planning Authority. Detail of soft landscaping shall include new planting focused around the existing access on the site that is to be removed. The approved scheme shall be implemented by the end of the full planting season immediately following the completion and/or first use of any separate part of the development (a full planting season means the period from October to March). The trees, shrubs and grass shall subsequently be maintained in accordance with the approved landscape maintenance scheme and any which die or are destroyed during this period shall be replaced during the next planting season.

Reason: To ensure an acceptable standard of landscaping, to ensure that the building is appropriately screened and to ensure the previous access is successfully replaced.
(Sections 12 & 15, NPPF)
4) Notwithstanding the information submitted within this planning application, the permission hereby granted shall only be used for the sole benefit of storage of equipment and machinery related to the equestrian use of the site, and shall not be used for any other purpose.

Reason: To ensure the retention of planning control by the Local Planning Authority on the disposal of the present applicant's interest in the land and buildings.
(Section 12, NPPF)
5) The development hereby permitted shall not be brought into use until details of the junction of the proposed vehicular access with the highway have been approved by the Local Planning Authority and the junction has been constructed in accordance with the approved details.

Reason: In order to minimise danger, obstruction and inconvenience to users of the highway and the premises.
(Section 9, NPPF)
6) The proposed vehicular access shall be surfaced in bituminous or other similar durable material (not loose aggregate) as may be approved in writing by the Local Planning Authority for a distance of 5m into the site, measured from the highway boundary, before the premises are brought into use. Arrangements shall be made for surface water drainage from the site to be intercepted and disposed of separately so that it does not discharge into the highway.

Reason: To avoid the carriage of mud or other extraneous material or surface water from the site into the highway so as to safeguard the interest of highway safety.
(Section 9, NPPF)
7) Before the new access is first brought into use, any existing access within the frontage of the land to be developed, not incorporated in the access hereby approved shall be closed in a manner to the Local Planning Authority's written approval and constructed in accordance with the approved details.
(See Notes to the Applicant)

Reason: In the interest of road safety and to reduce the number of points at which traffic will enter and leave the public highway.
(Section 9, NPPF)
8) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers 1904.PL.01A, 1904.PL.02A, 1904.PL.03.

Reason: To identify the approved plans and to avoid doubt.


Return to Search | Close WindowTop of Page