1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of the existing building.

Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials to match the existing building in the interests of the visual amenities of the locality.
(Section 12, NPPF)
3) Notwithstanding the provisions of Part 1, Class A of Schedule 2 to the Town and Country Planning (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), no extensions to the building known as Plot 2 on plan number 2122-00 Rev C hereby permitted shall be carried out without the grant of further specific planning permission from the Local Planning Authority.

Reason: To control the external appearance of the building/s in the interests of the amenities of the area.
(Section 12, NPPF)
4) Before the new access is first brought into use, a triangular vision splay shall be provided on each side of the access drive and shall be 2.8m measured along the back edge of the highway from the centre line of the anticipated vehicle path to a point 2.0m measured from the back edge of the highway into the site along the centre line of the anticipated vehicle path. The vision splay so described and on land under the applicant's control shall be maintained free of any obstruction to visibility exceeding a height of 600mm above the adjoining footway level.

Reason
To provide adequate visibility between the existing highway and the proposed access and to make the access safe and convenient for the traffic which is likely to use it.
5) The proposed driveway access shall be surfaced in bituminous or other similar durable material (not loose aggregate) as may be approved in writing by the Local Planning Authority for a minimum distance of 5m into the site, measured from the highway boundary, before the premises are occupied. Arrangements shall be made for surface water drainage from the site to be intercepted and disposed of separately so that it does not discharge into the highway.

Reason
To avoid the carriage of mud or other extraneous material or surface water from the site into the highway so as to safeguard the interest of highway safety.
6) The development hereby permitted shall be undertaken in full accordance with the Council's adopted 'Construction Code of Practice for Developers and Contractors' https://www.centralbedfordshire.gov.uk/info/44/planning/674/codes_of_practice_for_planning.
Reason: In order to minimise the impact of construction work on the amenities of nearby residential properties (Section 12, NPPF)
7) Prior to the construction of vehicular parking areas associated with the approved dwellinghouses, a scheme for the charging of electric vehicles shall be submitted to and approved in writing by the Local Planning Authority. Subsequently, the development shall be completed in accordance with these approved details.

Reason: To assist with the transition to low-emission vehicles in line with paragraph 110 of the National Planning Policy Framework (2019)
8) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers 2122-00 Rev C, 2122-01, 2122-02, 2212-03 Rev B, 2122-04 Rev D and 2122-05 Rev C.