<< Back to case
Conditions or Reasons for Planning Application - CB/19/03597/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers PD/1902 DR/A/023/P2, 021/P2, 101/P2, 022/P2, 010/P1, 200/P1, 020/P1, 022/P1, 10/P1, 011/P2, 024/P2, PD/19/002/A/201/P3, PD/19/002/A/012/P6 and PD/19/002/A/021/P3.
3) .In the event that contamination is found at any time when carrying out the approved development, it shall be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment shall then be undertaken by a competent person, in accordance with 'Model Procedures for the Management of Land Contamination, CLR 11'. A written report of the findings should be forwarded for approval to the Local Planning Authority. Following completion of remedial measures a verification report shall be prepared that demonstrates the effectiveness of the remediation carried out. No part of the development should be occupied until all remedial and validation works are approved in writing.

Reason: To ensure that no future investigation is required under Part 2A of the Environmental Protection Act 1990.
4) Before development/work begins and notwithstanding the details submitted with the application, details of the materials to be used for the external windows, doors, walls, roofs and rainwater goods of the proposed building/s shall be submitted to and approved in writing by the Local Planning Authority. The development/work shall be carried out only in accordance with the approved details.

Reason: To ensure that the development/work is in keeping with the existing building. (Section 16, NPPF)
5) No development shall take place until a scheme for protecting the proposed dwelling from noise from commercial and agricultural operations has been submitted to and approved in writing by the local planning authority. The dwelling shall not be occupied until such a scheme has been implemented in accordance with the approved details, and shown to be effective, and it shall be retained in accordance with those details thereafter.

Reason: To protect the amenity of future residents of the development and to safeguard existing commercial and agricultural uses.
6)
The access shall have a minimum width of 2.75m.

Reason
In the interest of road safety and for the avoidance of doubt.
7) Before the premises are occupied all on site vehicular areas shall be surfaced in a stable and durable materials in accordance with details to be approved in writing by the Local Planning Authority. Arrangements shall be made for surface water drainage from the site to soak away within the site so that it does not discharge into the highway or into the main drainage system.

Reason
To avoid the carriage of mud or other extraneous material or surface water from the site so as to safeguard the interest of highway safety and reduce the risk of flooding and to minimise inconvenience to users of the premises and ensure satisfactory parking of vehicles outside highway limits
8) The turning space for vehicles illustrated on the approved Plan (No PD-19-02-DR-A-012) shall be constructed before the development is first brought into use.

Reason
To enable vehicles to draw off, park and turn outside the highway limits thereby avoiding the reversing of vehicles on to the highway.
9) No development shall take place until a written scheme of archaeological investigation (WSI); that includes provision for fieldwork followed by post excavation analysis and publication, has been submitted to and approved in writing by the Local Planning Authority. The development hereby approved shall only be implemented in full accordance with the approved archaeological scheme and this condition will only be fully discharged when the post-excavation analysis and reporting is complete, and the future of the site archive is secured.'

Reason: This condition is pre-commencement as a failure to secure appropriate archaeological investigation in advance of development would be contrary to paragraph 199 of the National Planning Policy Framework (NPPF) that requires developers to record and advance of understanding of the significance of any heritage assets affected by development before they are lost (wholly or in part).
10) A bat loft must be provided in accordance with plan numbers: PD/19/002/A/201/P3, PD/19/002/A/012/P6 and PD/19/002/A/021/P3.
Reason: To safeguard bats at the site which are Protected Species.