<< Back to case
Conditions or Reasons for Planning Application - CB/19/03774/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) No above-ground works shall take place, notwithstanding the details submitted with the application, until details of the materials to be used for the external walls and roofs of the development hereby approved have been submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details.

Reason: To control the appearance of the building in the interests of the visual amenities of the locality.
(Section 12, NPPF)
3) Prior to first occupation of the dwellings hereby approved, the proposed vehicular access and on-site vehicular areas shall be surfaced in bituminous or other similar durable material (not loose aggregate) for a distance of 5m into the site, measured from the highway boundary, before the premises are occupied. Arrangements shall be made for surface water drainage from the site to be intercepted and disposed of separately so that it does not discharge into the highway.

Reason

To avoid the carriage of mud or other extraneous material or surface water from the site into the highway so as to safeguard the interest of highway safety.
4) A scheme shall be submitted for approval in writing by the Local Planning Authority indicating the positions, design, materials and type of boundary treatment to be erected. The boundary treatment shall be completed in accordance with the approved scheme before the dwellings hereby approved are occupied and be thereafter retained.

Reason: To safeguard the appearance of the completed development and the visual amenities of the locality and to ensure an appropriate standard of privacy for adjoining occupiers

(Section 12, NPPF)
5) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers CBC/01; ASC.18.523; JLG655/S2/01/ rev B.

Reason: To identify the approved plan/s and to avoid doubt.


Return to Search | Close WindowTop of Page