Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of the existing building.

Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials to match the existing building in the interests of the visual amenities of the locality.
(Section 12, NPPF)
3) Any gates provided shall open away from and not encroach upon the public highway.

Reason: In order to minimise danger, obstruction and inconvenience to users of the highway and of the premises.
(Section 9, NPPF)
4) Before the premises are occupied all on site vehicular areas shall be surfaced in a manner to the Local Planning Authority's approval so as to ensure satisfactory parking of vehicles outside highway limits. Arrangements shall be made for surface water from the site to be intercepted and disposed of separately so that it does not discharge into the highway.

Reason
In order to minimise danger, obstruction, and inconvenience to users of the highway and of the premises.
(Section 9, NPPF)
5) Prior to occupation a scheme for the provision of a refuse storage area and collection point shall be submitted to and approved in writing by the Local Planning Authority. The scheme hereby approved shall be available prior to occupation and retained for so long as the facility is in operation.

Reason: To ensure the refuse collection bins do not cause a hazard or obstruction to the highway or parking area.
(Section 9, NPPF)
6) Prior to occupation a scheme for the provision of secure cycle storage for residents and visitors shall be submitted to and approved in writing by the Local Planning Authority. The scheme hereby approved shall be available prior to occupation and retained for so long as the facility is in operation.

Reason: In order to promote sustainable modes of transport.
(Section 9, NPPF)
7) Before the development is first occupied or brought into use, the parking scheme shown on the approved drawing shall be completed and thereafter retained for this purpose.

Reason: To ensure the provision of car parking clear of the highway.
(Section 9, NPPF)
8) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers TLD 001, TLD 002, TLD 011, TLD 012, TLD 013, TLD 014, TLD 015, TLD 016, TLD 221, TLD 222, TLD 323, TLD 324, TLD 325 and TLD 326.

Reason: To identify the approved plan/s and to avoid doubt.
9) The second floor dormer window of the rear elevation of the development hereby permitted shall be permanently fitted with obscured glass of a type to substantially restrict vision through it at all times and non-opening, unless the parts of the window which can be opened are more than 1.7m above the floor of the room in which the window is installed.

Reason: To safeguard the privacy of occupiers of adjoining properties
(Section 12, NPPF)