Conditions or Reasons for Planning Application - CB/20/00418/DOC
Conditions or Reasons:
4) No dwelling hereby approved shall be occupied, until a Landscape, ecological and Sustainable Drainage System Maintenance and Management Plan for a period of ten years from the date of its delivery has been submitted to and approved in writing by the Local Planning Authority. The scheme shall include details of the management body, who will be responsible for delivering the approved maintenance and management plan. The landscaping and SuDs shall be maintained and managed in accordance with the approved plan following its delivery.

Reason: To ensure that the appearance of the site would be acceptable and a net gain in biodiversity could be retained, in accordance with Policy DM14 & DM15 of the Core Strategy and Sections 14 & 15 of the NPPF.
6) No development shall take place above slab level, until a sustainability statement has been submitted to and approved in writing by the Local Planning Authority demonstrating energy and water efficiency measures. The works shall then be carried out in accordance with the approved details.

Reason: This condition is pre-commencement of above slab level as many energy efficiencies relate to fabric first approach which will be required to be ordered in advance of construction start and in the interests of sustainability. (Policy DM2 of the Core Strategy for the North & Section 14 of the NPPF)
22) No development shall be commenced above slab level, until an estate street phasing and completion plan has been submitted to and approved in writing by the local planning authority. The estate street phasing and completion plan shall set out the development phases and the standards that estate streets serving each phase of the development will be completed.

Reason: This condition is pre-commencement to ensure that the estate streets serving the development are completed and thereafter maintained to an acceptable standard in the interest of residential / highway safety; to ensure a satisfactory appearance to the highways infrastructure serving the development; and to safeguard the visual amenities of the locality and users of the highway, in accordance with Policies DM3 of the Core Strategy and Sections 9 & 12 of the NPPF.
27) No dwelling shall be occupied until (a) revised refuse collection points, (b) increase of initial 8m of private drives to 4.8m and (c) traffic calming on the section of road serving plots 112 to 137 has been provided in accordance with details of a scheme to be submitted to and approved by the Local Planning Authority.

Reason: In the interests of road safety and pedestrian movement. (Section 4, NPPF)