1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) Prior to the commencement of works above ground level, details of the construction materials for the external walls and roof and other features and apparatus of the development hereby approved, shall be submitted to the Local Planning Authority for approval in writing. The development shall thereafter be carried out in accordance with the approved details.

Reason: To control the appearance of the building in the interests of the visual amenities of the locality, in accordance with Policies CS14 and DM4 of the adopted Local Plan, Policy HQ1 of the emerging Local Plan, the adopted Design Guide and the NPPF.
3) The development hereby permitted shall not be occupied or brought into use until the details of any external lighting to be installed on the site, including the design of the lighting unit, any supporting structure and the extent of the area to be illuminated, have been submitted to and approved in writing by the Local Planning Authority. The external lighting shall be installed in accordance with the approved details.

Reason: To protect the visual amenity of the site and its surrounding area.
(Section 12, NPPF)
4) Before the development is brought into use, the proposed development shall be carried out and completed in all respects in accordance with the access siting and layout illustrated on the approved plan No. 1473-BFF-ZZ-00-GA-A-0104-P1 and 1473-BFF-T1-00-GA-A-0105 -P1 and defined by this permission and, notwithstanding the provision of the Town and Country Planning General Permitted Development Order 1995, (or any Order revoking or re-enacting that Order) there shall be no variation without the prior approval in writing of the Local Planning Authority.

Reason: To ensure that the development of the site is completed insofar as its various parts are interrelated and dependent one upon another and to provide adequate and appropriate access arrangements at all times.
5) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers:
GA-A-0100 Rev P1 Master Site Location Plano
GA-A-0101 Rev P1 Site Location Plan
GA-A-0102 Rev P1 Block Plan (Existing)
GA-A-0103 Rev P1 Block Plan (Proposed)
GA-A-0104 Rev P1 Proposed Site Layout Plan
GA-A-0105 Rev P1 Proposed Ground Floor Plan
GA-A-0106 Rev P1 Proposed First Floor Intermediate Deck Plan
GA-A-0107 Rev P1 Proposed Second Floor Intermediate Deck Plan
GA-A-0108 Rev P1 Proposed Top Deck Plan
ELE-A-0112 Rev P2 Proposed North Elevation 1
ELE-A-0115 Rev P1 Proposed North Elevation 2
ELE-A-0110 Rev P2 Proposed South Elevation 1
ELE-A-0114 Rev P1 -Proposed South Elevation 2
ELE-A-0113 Rev P2 Proposed Section A-A
1473-BFF-T1-ZZ-ELE-A-0411-C2 Thales Tower North And South Cladding Setting Out

Reason: To identify the approved plan/s and to avoid doubt.