Conditions or Reasons for Planning Application - CB/20/00652/DOC
Conditions or Reasons:
12) No development shall take place, including any works of demolition, until a Construction Method Statement has been submitted to, and approved in writing by the local planning authority. The Statement shall provide
for:
i) the parking of vehicles of site operatives and visitors;
ii) loading and unloading of plant and materials;
iii) storage of plant and materials used in constructing the development;
iv) the erection and maintenance of security hoarding including decorative displays and facilities for public viewing, where appropriate;
v) wheel washing facilities;
vi) measures to control the emission of dust and dirt during construction;
vii) a scheme for recycling/disposing of waste resulting from demolition and construction works;
viii) delivery, demolition and construction working hours.
The approved Construction Method Statement shall be adhered to throughout the construction period for the development.