<< Back to case
Conditions or Reasons for Planning Application - CB/20/01240/DOC
Conditions or Reasons:
1) Within two months of the date of this permission the details of any external lighting to be installed on the site, including the design of the lighting, any supporting structure which must not exceed 4.5m in height and the extent of the area to be illuminated, should be submitted to the Local Planning Authority for approval. The approved lighting scheme shall be installed within 4 months of the date of the approved details. The lighting hereby approved shall not operate between the hours of 9pm and 6am.

Reason: To protect the visual amenity of the area and to minimise lighting pollution. (Section 12 and 13, NPPF)
3) Within two months of the date of this permission the details of any external CCTV systems to be installed on the site, including the design of any supporting structure, which should not exceed 4.5m in height, should be submitted to the Local Planning Authority for approval. The approved CCTV system shall be installed within 4 months of the date of the approved details.

Reason: To protect the visual amenity of the area. (Section 12 and 13, NPPF)
7) Within two months of the date of the permission and prior to occupation of Parcel B (as identified in the Planning Statement dated 5th December 2018 by Optimis Consulting), a Landscape Works and Maintenance Specification shall be submitted to the Local Planning Authority for approval, setting out the procedures for implementing and maintaining the landscaping scheme as submitted in the drawing Proposed Site Plan Landscaping Proposals -Revision A. The approved Landscaping Works and Maintenance Specification shall then be implemented as part of all landscape preparation works, planting operations and aftercare, which shall include an appropriate weed control and watering programme. The maintenance and aftercare period shall be for a minimum period of 5 years, with any losses replaced in accordance with the approved "Proposed Site Plan Landscaping Proposals" drawing.

Reason: To ensure that satisfactory horticultural best practice is undertaken as part of all landscape operations, in order to ensure the health and successful establishment of all landscaping planting.
(Section 15, NPPF)
8) Notwithstanding the approved landscaping, full details of a scheme for under planting, which should comprise of evergreen species, shall be submitted to the local planning authority within two months of the date of this permission. The approved scheme shall be implemented by the end of the full planting season immediately following the date of the approval of details (a full planting season means the period from October to March). The planting shall subsequently be maintained in accordance with the approved landscape maintenance scheme and any which die or are destroyed during this period shall be replaced during the next planting season.

Reason: To ensure an acceptable standard of landscaping and to safeguard the visual amenities of the surrounding area. (Section 12, NPPF)
11) Within two months of the date of this permission, confirmation in writing should be provided to the local planning authority that the watercourse culvert under the A5 Watling Street is suitable to handle additional surface water run-off from the impermeable area.

Reason: In the interest of ensuring appropriate drainage provision and to prevent flooding.(Section 14, NPPF)
12) Within two months of the date of this decision, full details of the balancing facility to be used as the means of storm water disposal, should be submitted to the local planning authority. Within 4 months, or unless otherwise agreed in writing, the details shall be implemented in accordance with the approved scheme.

Reason: In the interest of ensuring appropriate drainage provision and to prevent flooding.(Section 14, NPPF)
14) Within two months of the date of this permission, a Traffic Management Plan shall be submitted to the local planning authority for approval. The scheme shall include the following:
a. A plan for directing HGV drivers onto the Strategic Road Network and avoiding areas that have weight restrictions in place;
b. A series of measures to ensure existing and future HGV drivers undertaking deliveries to and from the site are aware of the restrictions in the local area;
c. A package of measures for monitoring the Traffic Management Plan.
The approved Traffic Management Plan shall be implemented for so long as the site is occupied for storage purposes.

Reason: To minimise the impact of the proposal on the surrounding highway network. (Section 9, NPPF)


Return to Search | Close WindowTop of Page