Conditions or Reasons for Planning Application - CB/20/02240/DOC
Conditions or Reasons:
2) No development shall take place until details of the existing and final ground and slab levels of the buildings hereby approved have been submitted to and approved in writing by the Local Planning Authority. Such details shall include sections through both the site and the adjoining properties, the location of which shall first be agreed in writing with the Local Planning Authority. Thereafter the site shall be developed in full accordance with the approved details.

Reason: To ensure that an acceptable relationship results between the new development and adjacent buildings and public areas.
(Section 7, NPPF)

This pre-commencement condition is necessary in order to ensure that no unnecessary harm is caused by the commencement of development works.
3) No development shall commence until a detailed surface water drainage scheme for the site, based on the agreed Drainage Strategy (April 2017), has been submitted to and approved in writing by the Local Planning Authority. The scheme shall include provision of attenuation for the 1 in 100 year event (+30% allowance for climate change) and show 40% exceedence routes. Any revisions to the agreed strategy shall be fully justified and approved before the development is completed and shall be managed and maintained thereafter in accordance with the agreed management and maintenance plan. Details of how the system will be constructed including any phasing of the scheme, and how it will be managed and maintained after completion will also be included.

The scheme shall be implemented in accordance with the approved final details before the development is completed, and shall be managed and maintained thereafter in accordance with the agreed management and maintenance plan.

Reason: To ensure the approved system will function to a satisfactory minimum standard of operation and maintenance and prevent the increased risk of flooding both on and off site, in accordance with para 103 NPPF.

This pre-commencement condition is necessary in order to ensure that no unnecessary harm is caused by the commencement of development works.
4) No development shall take place, including any works of demolition, until a Construction Traffic Management Plan, associated with the development of the site, has been submitted and approved in writing by the Local Planning Authority which will include information on:
The parking of vehicles
Loading and unloading of plant and materials used in the development
Storage of plant and materials used in the development
The erection and maintenance of security hoarding / scaffolding affecting the highway if required.
Wheel washing facilities
Measures on site to control the deposition of dirt / mud on surrounding roads during the development.
Footpath/footway/cycleway or road closures needed during the development period
Traffic management needed during the development period.
Times, routes and means of access and egress for construction traffic and delivery vehicles (including the import of materials and the removal of waste from the site) during the development of the site.

The approved Construction Management Plan associated with the development of the site shall be adhered to throughout the development process.

REASON: In the interests of safety, protecting the amenity of local land uses, neighbouring residents and highway safety.

This pre-commencement condition is necessary in order to ensure that no unnecessary harm is caused by the commencement of development works.