Conditions or Reasons for Planning Application - CB/20/02817/DOC
Conditions or Reasons:
1) No development shall commence until a detailed surface water drainage scheme, to manage surface water runoff from the development for up to and including the 1 in 100 year event (+40%CC), and a maintenance and management plan for the scheme has been submitted to and approved in writing by the Local Planning Authority. The discharge rate from this parcel will be limited to the 19.5l/s as per the agreed strategic site wide drainage strategy. The final detailed design shall be based on the agreed Below Ground Drainage Layout (Ref: 3000, Dated 23/10/2019) and DEFRAs Non-statutory technical standards for sustainable drainage systems (March 2018) and shall be implemented and maintained as approved. Any variation to the connections and controls indicated on the approved drawing which may be necessary at the time of construction would require the resubmission of those details to the Local Planning Authority for approval.

Reason: To ensure the approved system will function to a satisfactory minimum standard of operation and maintenance and prevent the increased risk of flooding both on and off site, in accordance with para 163 and 165 of the NPPF and its supporting technical guidance.
3) No development shall take place until an Ecological Enhancement Strategy (EES) for the creation of new wildlife features such as hibernacula, the inclusion of integrated bird/bat and bee boxes in buildings/structures, hedgehog holes in fences and tree, hedgerow, shrub and wildflower planting/establishment has been submitted to and approved in writing by the local planning authority. The content shall include the:

a) purpose and objectives for the proposed works;
b) detailed design(s) and/or working method(s) necessary to achieve stated objectives (including, where relevant, type and source of materials to be used);
c) extent and location of proposed works shown on appropriate scale maps and plans;
d) timetable for implementation, demonstrating that works are aligned with the proposed phasing of construction;
e) persons responsible for implementing the works;
f) details of initial aftercare and long-term maintenance.

The works shall be carried out strictly in accordance with the approved details and shall be retained in that manner thereafter

Reason: To ensure development is ecologically sensitive and secures biodiversity enhancements in accordance with the National Planning Policy Framework.