Conditions or Reasons for Planning Application - CB/20/03759/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) No works for the new dwelling hereby approved shall take place until a detailed surface water drainage scheme, to manage surface water runoff from the development for up to and including the 1 in 100 year event (+40%CC), and a maintenance and management plan for the scheme has been submitted to and approved in writing by the Local Planning Authority. The discharge rate from the development will be limited to the equivalent 1 in 1 year rate, or an appropriate rate as agreed by the Bedford Group of Internal Drainage Boards. The final detailed design shall be based on the agreed drainage Strategy (Ref: to be submitted) and DEFRAs Non-statutory technical standards for sustainable drainage systems (March 2018) and shall be implemented and maintained as approved. Maintenance will ensure the system functions as designed for the lifetime of the development. Any variation to the connections and controls indicated on the approved drawing which may be necessary at the time of construction would require the resubmission of those details to the Local Planning Authority for approval.

The applicant should address points 1, 2, 3, 4 and 6 (of advisory note 1) when submitting details to discharge the condition

Reason: To ensure the approved system will function to a satisfactory minimum standard of operation and maintenance and prevent the increased risk of flooding both on and off site, in accordance with para 163 and 165 of the NPPF and its supporting technical guidance.
3) Notwithstanding the provisions of Part 1 Class E of Schedule 2 to the Town and Country (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), no buildings or other structures shall be erected or constructed within the curtilage of the property without the grant of further specific permission from the Local Planning Authority.

Reason: To control the development in the interests of preserving the openness of the Green Belt (Chapter 13, NPPF).
4) Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), no extensions to the building hereby permitted shall be carried out without the grant of further specific permission from the Local Planning Authority.

Reason: To control the external appearance of the building in the interests of preserving the openness of the Green Belt and the visual appearance of the street scene.
(Policies BE8 S.B.L.P.R).
5) It is recommended that any gates provided shall open away from the access road and be set back a distance of at least 5.0m within the site.

Reason: To enable vehicles to draw off the access road before the gates are opened.
6) No building/dwelling shall be occupied until the developer has formally submitted in writing to the Local Planning Authority a finalised 'Maintenance and Management Plan' for the entire surface water drainage system, inclusive of any adoption arrangements and/or private ownership or responsibilities, and that the approved surface water drainage scheme has been correctly and fully installed as per the final approved details.

Reason: To ensure that the implementation and long term operation of a sustainable drainage system (SuDS) is in line with what has been approved, in accordance with Written Statement HCWS161, 18th December 2014.
7) The development hereby permitted shall be undertaken in full accordance with the Council's adopted 'Construction Code of Practice for Developers and Contractors' https://www.centralbedfordshire.gov.uk/info/44/planning/674/codes_of_practice_for_planning.

Reason: In order to minimise the impact of construction work on the amenities of nearby residential properties (Section 12, NPPF)
8) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers 19/079/03B; 19.079.02A; 19.079.01; EV05; EV04; EV02; EV01; EV03.

Reason: To identify the approved plan/s and to avoid doubt.